Every duration is in working days on the project's own calendar: the working days after the start day, up to and including the end day. Each measure is worked out as of the night it was counted, from the dates on the records.
Draft and cancelled RFIs, draft submittals and cancelled punch items are left out of every measure.
| Column | Measure | How it's worked out | Better is |
|---|---|---|---|
| RFI time | RFI answer time (median) | For each answered RFI, working days from raised to answered. The middle of those. | Lower |
| RFI late | RFIs past required date | Of the RFIs that had a required-by date and are now due (answered, or past the date), the share answered late or still unanswered. | Lower |
| Sub. time | Submittal review time (median) | For each submission that has come back, including resubmissions, working days from submitted to returned. The middle of those. | Lower |
| Resubmit | Resubmittal rate | Of the submissions returned with a decision, the share that came back Revise and Resubmit, Rejected or Not Reviewed. Voided submissions aren't counted. | Lower |
| Sub. late | Submittals past required-by | The same as RFI late, for submissions and their returned dates. | Lower |
| Punch time | Punch close time (median) | For each completed punch item, working days from raised to complete. The middle of those. | Lower |
| Punch age | Open punch age (median) | For each punch item still open (not draft, not complete), working days since it was raised. The middle of those. | Lower |
| Finish | Projected finish vs contract | Working days between the contract completion date and the projected finish. Positive (+) means the projected finish is later than the contract. The projected finish is the end of the project's current schedule. | Lower |
| Dailies | Daily reports filed | Of the last 30 working days (up to the day, or up to the completed date for a closed project, and not before the project started), the share that have a daily report other than an Open one. | Higher |
Why a cell has no figure
| It says | Because |
|---|---|
| too few items | Fewer than 5 items to measure: for example fewer than 5 answered RFIs, or fewer than 5 working days to check for daily reports. A figure from so few would swing too much to compare. |
| none open | Open punch age, on a project with no punch item open. |
| no schedule data | Finish, on a project missing its contract completion date or a current schedule. |
A measure without a figure doesn't count towards the project's score, in either direction.
Note
Finish compares the projected finish with the contract completion date. There's no schedule baseline in it.