Every project scored against the rest of the portfolio, which ones need attention or are ahead, and how to filter and sort the table.

Who this is forExecutives, Company admins

Permission neededReporting — Portfolio

Project Health compares every project with the others on nine measures, from RFI answer time to daily reports filed, and gives each one a score from 0 to 100. It covers every project in the workspace, whichever projects you're on, so only people with the Portfolio level of Reporting see it.

Project Health
The filters, the Projects and Firms tabs, the headline, the totals and the dot strip.

Which projects are included

Every project in the workspace except deleted ones and Draft projects. A closed project (one with a completed date) stays in for 24 months after it was completed, then drops out.

The figures are worked out every night from each project's RFIs, submittals, punch items, schedule dates and daily reports. They're as of the date in the headline, usually yesterday. A new project is scored the night after it's added; until then it isn't in the table, and a note under the table says how many projects aren't scored yet.

Filter the projects

  1. Under Projects, click All, Active or Closed. This applies straight away.
  2. Choose a Type, Office or Stage, or leave them on All.
  3. Click Apply.

Click Clear to remove the filters. Every figure, including each score, is worked out again against only the projects you've kept, so a project's score can change when you filter.

The headline and totals

The headline sentence is written from the figures: how many projects need attention and how many are ahead, an architect most of the "needs attention" projects share (when two or more do), and the median RFI answer time.

  • Projects scored: projects with at least one measure scored, of those shown.
  • Needs attention and Ahead: projects well below or well above the rest (see below).
  • Median RFI answer time: the middle of the projects' RFI answer times, in working days.

How the score works

  1. Each measure is ranked across the projects shown. For each measure, a project gets a percentile: 100 means it's the best of the projects shown, 0 the worst, and projects with the same figure share the middle. A measure is only scored on a project with at least 5 items (5 answered RFIs, for example), and only when at least two projects are scored on it.
  2. The score is the average of a project's percentiles over the measures it's scored on. A project with no measure scored says not scored.

See How the Project Health measures are worked out for each measure.

Needs attention and Ahead

Once 8 or more projects are scored, the report works out a normal range around the middle score, based on how spread out the scores are. A project scoring below that range is marked ▼ Needs attention; one scoring above it is marked ▲ Ahead. With fewer than 8 scored projects, nobody is marked.

Where each project sits shows one dot per scored project, from worse on the left to better on the right. The shaded band is the normal range and the dashed line is the median. Projects outside the band are labelled. Point at a dot to see the project and score; click it to open the project's measures.

The table

Health score by project
Each project's score, its trend, and its nine measures, coloured by percentile.

Health score by project shows each project's number, type, office and stage under its name, then:

  • Score, with its Needs attention or Ahead badge.
  • 6 mo: the score at the end of each of the last six months, each worked out against the projects shown as they stood then. The end dot is blue if the score rose over that time and red if it fell. "no history" means no month has a score yet.
  • The nine measures. Each cell is shaded red when it's worse than most projects, blue when it's better, and grey around the middle. Point at a cell to see its percentile and how many items it covers. A cell may say too few items, none open or no schedule data instead of a figure.

Sort the table

The table starts with the lowest score first, so the projects that most need reading are at the top. Click a column heading to sort by it; click it again to reverse. Sorting by a measure sorts by its percentile, worst first.

Click a project's name to open its measures in a side panel. See Open a project's measures.

The filters, sort, tab and open panel are all part of the page address, so you can bookmark or share exactly what you're looking at.

Empty pages

  • No project scores yet: the projects haven't been worked out yet. The first scores appear the night after.
  • No projects match: no project fits the filters.