Pre-fill the submittal manager, due date, required responses and distribution recipients, for your whole company or one project.

Who this is forCompany admins, Project admins

Permission neededSettings — Admin (company); Project administration — Admin (project); Directory — Manage Companies and Users (default recipients)

Defaults save time when logging submittals. They pre-fill the Submittal manager and Final due date on the New submittal form, set whether people on a new workflow step start as required, and choose who distributions go to. People can still change them on each submittal.

Changing a default only affects submittals logged afterwards.

Set company defaults

  1. Go to Settings and open Module defaults.
  2. Find the Submittals card.
  3. Set:
    • Submittal manager: the person pre-selected as manager on new submittals. They're only pre-selected on projects where they're in the project directory.
    • Work days until due: how many work days after the submittal is logged its final due date should be. Leave it blank for no default.
    • Approver response required by default: whether the required tick starts ticked for each person on a new workflow step.
    • Distribution group: who a new project's default submittal recipients start as.
  4. Click Save submittal defaults.

Set defaults for one project

  1. Open the project and choose Admin in the sidebar.
  2. Under Module settings, find the Submittals card. It says whether the project is following the workspace defaults or overriding them.
  3. Set Submittal manager, Work days until due and/or Approver response required by default (Required, Optional, or the workspace default).
  4. Click Save submittal settings.

To go back to the company defaults, click Use workspace defaults.

Choose who distributions go to by default

Each project keeps a list of default submittal recipients. When anyone clicks Close & Distribute, these people and groups start ticked.

  1. Open the project and choose Admin in the sidebar.
  2. Find Default recipients and the Submittal row, then click Edit.
  3. Move people and groups between Available and Selected.
  4. Click Save Submittal.

When a project is created, this list starts from the Distribution group in the company's Submittals defaults.

How due dates are counted

Work days are counted on the project's calendar: its working week and, where it observes them, holidays.