What each section records

The fields on every kind of daily report entry, and which ones must be filled in before it can be added.

Who this is forSuperintendents, Field engineers, Project managers

Every entry also has a Location (picked from the project's locations; type a name that isn't there and choose Add "…" as a new location to add it), and most have a Description in your own words. Press Enter to start a new line, and use the buttons above the box for Bold, Italic, Underline, a Bulleted list or a Numbered list. Typing - at the start of a line also starts a bulleted list. Fields marked with * on the form must be filled in. Some sections instead need at least one of a few fields; the form tells you which if you leave them all empty.

Your company can add its own fields to each kind of entry. They come after the fields below, on the form and as columns of the section. See Add your own fields.

Times on an entry (Started, Arrived, Delivered at and so on) are just a time. The date is the day you're on. If an end time is earlier than its start, like a delay from 10:00 PM to 1:30 AM, the end goes on the next day and shows its date.

Section Fields You must fill in
Weather Observations Observed at, Temperature (°F), Conditions, Caused delays The conditions, the temperature or a description
Manpower Subcontractor, Workers on site, Hours each, Work performed, Cost code, Foreman, Count toward labor hours Workers on site
Notes Description, Location Description
Delays Delay type, Started, Ended, Duration (minutes) The delay type, when it started, how long it lasted, or a description
Waste Material, Disposed by, Method, Disposal location, Approximate quantity, Hazardous, Disposed at Material
Extra Work Performed by, Work performed, Reason, Authorized by, Workers, Hours each, Materials used, Equipment used, Charge to, T&M ticket #, Hourly rate Work performed
Equipment Logs Equipment, Hours used, Idle on site Equipment
Dumpsters Hauler, Delivered, Removed How many were delivered or removed
Visitors Visitor, Company, Purpose, Arrived, Departed Visitor
Time Cards Person, Cost code, Hours, Billable Person
Purchases Item, Cost code, Quantity, Total expense Item
Accidents Person involved, Their company, Occurred at, Injury, Treatment given, Reportable (OSHA) The person involved, the injury or a description
Inspections Inspecting body, Inspector, What was inspected, Outcome, Started, Ended What was inspected, the inspector, the inspecting body, the outcome or a description
Safety Violations Issued to, Their company, Occurred at, Notice, Compliance due Who it was issued to, the notice or a description
Phone Calls Caller, Other party, Time, Duration (minutes) Caller
Deliveries Supplier, Tracking number, Delivered at The supplier, a tracking number or a description

Charge to on Extra Work is one of Owner (change order), Backcharge or Our cost.

Counts, hours, quantities, costs and durations can't be below zero.

Totals

Sections with counts or hours show a Total row: workers, hours, deliveries and removals, durations, quantities and expenses. Manpower also shows the day's labor hours: each crew's workers times hours each, added up.

Dumpsters also show the project's running totals beside the section's name, from the first day through the day you're on: Total Project Dumpsters is every dumpster delivered, and Total Project Dumpster Empties is every one removed. They're worked out from each day's Delivered and Removed, so changing an earlier day updates the totals on every day after it. The totals appear once the project has had a dumpster delivered or removed, and they're printed under Dumpsters on the PDF.

Manpower with totals
Only the columns somebody filled in that day are shown.

People on an entry

Fields such as Caller and Person are picked from the project directory. If the person isn't there, type their name and choose Add "…" as a new person, then fill in their first name, last name and company. They're added to the project directory when you save the entry.

Foreman, Visitor, Inspector and Other party are picked from the project directory too. Someone who isn't in it, such as a sub's foreman, a city inspector or a courier, doesn't need to be added: choose Not in the directory? Type a name and type it. The name is kept on the entry only.

When you pick a Foreman, Inspector, Visitor, Person involved or Issued to from the directory and leave the company empty, the entry takes that person's company when you save it.

An accident is recorded once for each person involved. To add someone else hurt in the same accident, click the person icon at the end of its row: a new accident opens with the same time, description and location, ready for the next person.

Companies and equipment

Subcontractor, Hauler, Supplier and the other company fields list the companies on the project, with each one's trade. To offer another company, add it to the project's directory. Hauler, Supplier, Disposed by, Inspecting body and a visitor's Company also take a typed name for a company that isn't in the directory, such as a utility, a courier or the city. It's kept on the entry, offered again on the project's later reports, and never added to the directory. Equipment lists the project's equipment first, then From the organization list; picking an organization item adds it to the project as the entry is saved.

A delay's Duration (minutes) is worked out from Started and Ended as you enter them. Type it yourself only when you don't know the times.

Delay type lists the project's delay reasons: the workspace's Delay reasons in Dropdown Options, or the project's own list if it has changed it. An entry keeps its delay type when that reason is later retired.