Manage schedule templates

Add templates from the StruXure library, write your own, and edit the tasks, subtasks and milestones a project can insert into its schedule.

Who this is forCompany admins, Schedulers

Permission neededSettings — Admin

A schedule template is a set of tasks, subtasks and milestones, each with a number of working days, such as "Concrete foundation" or "Closeout and turnover". On a project's schedule, someone picks a template and a start date, and its tasks are inserted, laid out on the project's working days. Templates stack: inserting one never replaces what is already there.

Go to Settings and open Schedule templates. Your templates are the ones your projects can insert. The StruXure library below is a set of starter templates you can copy in.

The Schedule templates page

Each template shows how many tasks and milestones it has, and how many working days it spans.

Add a template from the StruXure library

  1. Under StruXure library, find the template.
  2. Click Add beside it.

A copy is added to Your templates, marked From the StruXure library, and the library row now says In your templates.

The StruXure library

Write a template

  1. Under New template, type a Name and, if you like, a Description.
  2. Type the Tasks, one per line:
    • End a line with | and the number of working days, such as Pour footings | 1. A line without a number takes 1 day.
    • | 0 makes a milestone, such as Footing inspection | 0.
    • Indent a line two spaces to put it under the line above, as a subtask.
    • Tasks follow one another in the order written.
  3. Click Add template.
The New template form

You can also save a project's own schedule as a template, with Save as template on the project's schedule.

Edit a template

  1. Click Edit on the template's row.

  2. Change the name, description or tasks.

  3. Click Save.

    Editing a template

The page says Saved "…". Schedules it was already inserted into are unchanged.

Note

A template saved from a project keeps that schedule's own links between tasks. Saving it here links the tasks one after another instead, in the order written.

Delete a template

  1. Click Edit on the template's row, then Delete template.
  2. Confirm with Delete template.

Projects can no longer insert it. Schedules it was already inserted into keep their tasks.

For inserting a template into a project's schedule, see Insert a schedule template.

If a template is refused

Message What to do
A template needs a name. Type a name.
There is already a template called "…". Choose another name.
A template needs at least one task. Add at least one line.
Line … is indented, but there is nothing above it to sit under. Take the indent off the first line.
Line … is indented more than one step under the line above it. Indent by two spaces at a time.
Line …: "…" is not a whole number of days. Use a whole number after the `