StruXure
/

Choose read only or full control

Decide whether a project's schedule is read only and changed by importing a file, or edited here with full control. Or clear the schedule and start again.

Who this is forProject managers, Schedulers

Permission neededSchedule — Edit / Import Schedules

Your company sets the choice for new projects in Settings › Scheduling. Each project can follow that or make its own choice.

Setting Edit on the Gantt chart Import a file Restore from the history
Read only No. Nobody edits the schedule here. Yes. Each import replaces the schedule. Yes. The restored version is read only too.
Full control Yes, with Edit access. Yes. The file becomes the schedule you edit, and the version it replaces stays in the history. Yes. You get a copy of that version to edit.

Change the setting

  1. Open the project's Schedule and click Schedule settings.
  2. Under How the schedule is changed, choose one:
    • Follow the organization: whatever your company has chosen, shown in brackets.
    • Read only: changed only by importing a schedule file. Each import replaces it. Nobody edits it here.
    • Full control: edited here on the Gantt chart. You can still import a file; the version it replaces stays in the history.
  3. Click Save settings.

The line under the choices says what the project uses Now.

Choosing Full control while an imported schedule is showing does the same as Switch to full control: the schedule becomes a copy you edit here, and the imported file stays in the history. See Build a schedule in StruXure.

Choosing Read only on a project with full control stops editing. Your edited version is kept as it was; the next import replaces it, and the edited version stays in the history.

Note

If your company has switched off full control, Full control can't be chosen and says "Full control is switched off for this organization." A project that had full control then shows its schedule read only, and Now says so.

Clear the schedule

Use this to start again on a project: for example, the wrong file was imported, or you want to switch from a file to building it here with a clean slate.

  1. Open Schedule settings.
  2. At the bottom, under Clear schedule, click Clear schedule.
  3. Read the confirmation and click Clear schedule.

The project shows no schedule: the Gantt chart, calendar, milestones and the dashboard's schedule cards are empty until a schedule is imported or built. The page says "The schedule was cleared." Nothing is deleted. Every version stays in the history under Import schedule and can be restored. See Restore an earlier version.