If you're the one who keeps the job's schedule, this is the path through it from the first day to the last.
1. Set up the project's calendar
Before you load anything, open Schedule and click Schedule settings. Check the Working week and Holidays, and add any known shutdown days under Days that break the week. Every length and lag is counted on these days. See Set the project's working days.
2. Decide read only or full control
- You schedule in Microsoft Project. Leave the setting on Read only (or following the organization, if that's your company's default). Go to step 3a.
- You'd rather build it here. Choose Full control, or just use Build a schedule or Start from a template on the empty page. Go to step 3b.
See Choose read only or full control.
3a. Keep it current from Microsoft Project
- Click Import schedule, drop your .mpp, .xml or .xer file on the panel, and click Import. See Import a schedule from Microsoft Project or Primavera P6.
- Each time you update dates or progress in Microsoft Project, import the file again. The new file replaces the schedule; the old one stays in the history.
- If an import was a mistake, click Restore on the previous file in the history. See Restore an earlier version.
If you later decide to stop using Microsoft Project, click Switch to full control and carry on with 3b.
3b. Build and keep it in StruXure
- Insert templates for the phases you know, from the start dates you want. See Insert a schedule template.
- Add, rename, move and indent tasks; set lengths in working days. See Add and arrange tasks.
- Link tasks so later work follows earlier work. See Link tasks with dependencies.
- As work goes on, set Progress on each task, and drag bars when dates change. Every change saves as you go.
- Check Critical Path to see which activities drive the finish date.
4. Share it
- Give the team Read on the schedule so they see it, and the dashboard's Today's Tasks and Pending Milestones. Give anyone who helps keep it Edit. See Who can do what on the schedule.
- Send a link to the exact tab, month or milestone list you're looking at; the link opens the same view.
- Use Print for a PDF of the Gantt chart for a meeting, and Export CSV for a spreadsheet. See Export or print the schedule.
5. Starting over
If the project's schedule needs to start fresh, use Clear schedule at the bottom of Schedule settings. Nothing is deleted, and every version can still be restored.