The Gantt tab is where the schedule opens. The activity list is on the left and the bar chart on the right.

The columns
| Column | What it shows |
|---|---|
| ID | The activity's row number, as in Microsoft Project. Dependencies refer to activities by this number. |
| Task Name | The activity. Indented rows sit under a summary row; click the arrow beside a summary to fold or unfold it. Point at a long name to read all of it. An amber tag such as +5d before the name means open records expect to delay it; point at the tag to see which, or click it to open one. See See proposed delays on the schedule. |
| Start and Finish | The first and last day of the activity. |
| Days | How long the activity is. A milestone is 0. |
| Progress | How far along it is, as a percentage. |
| Predecessors | What this activity waits on, written the way Microsoft Project writes it. |
Reading the Predecessors column:
| You see | It means |
|---|---|
12 |
Starts after activity 12 finishes (finish-to-start). |
12SS |
Starts when activity 12 starts (start-to-start). |
12FF |
Finishes when activity 12 finishes (finish-to-finish). |
12SF |
Finishes when activity 12 starts (start-to-finish). |
12FS+3d |
Starts 3 working days after activity 12 finishes. A minus sign, such as 12FS-2d, means it starts 2 working days before. |
Several predecessors are separated by commas. You can drag the edges of the column headings to make a column wider, and drag the line between the list and the chart to give either more room.
An activity with no dates shows dashes in its date columns and has no bar.
The chart
- Grey bars are summary rows, spanning everything under them.
- Blue bars are tasks. The darker part of a bar is the progress.
- Green diamonds are milestones.
- Arrows between bars are dependencies.
- The red vertical line is today, labelled with today's date.
Point at a bar to see its name, its dates and its progress.
The toolbar

- Hours, Days, Months and Years zoom the chart. The highlighted button is the zoom you're on. The chart opens at Years, or at Months when you're editing a schedule with full control. At Days, days off (weekends, holidays and the project's own days off) are shaded grey.
- Critical Path colours the critical path red: the activities and dependencies with no room to slip, where any delay moves the end of the job. Click Hide Path to turn it off again.
- Hide Links hides the dependency arrows, which helps on a busy schedule. Click Show Links to bring them back.

The critical path is worked out by StruXure on the project's working days, each time a schedule is imported or saved.
Opening the chart at an activity
A link to an activity from elsewhere, such as a submittal's Schedule activity, opens the Gantt chart with that activity selected and scrolled into view. Clicking a band on the Calendar tab or a milestone on the Milestones tab also brings you back to the Gantt chart.