Who can do what on the schedule

The three levels of schedule access, what each allows, which standard roles have them, and what people without access see.

Who this is forCompany admins, Project admins

Access to the schedule comes from the roles people hold, at company level or on a project. In the roles screen, the area is called Schedule, with three levels.

The three levels

Level What it allows
Read Open the schedule: the Gantt chart, calendar and milestones. Turn on the critical path, zoom, export to CSV and print. See the schedule cards on the project dashboard.
Edit Everything in Read, plus: change a schedule that is built in StruXure. Add, move, link and delete tasks and milestones, and insert schedule templates.
Edit / Import Schedules Everything in Edit, plus: import a file from Microsoft Project or Primavera P6, restore, download and remove earlier versions, build a schedule or take over an imported one with Switch to full control, change the project's Schedule settings (read only or full control, working week, holidays, single days), and clear the schedule.

Save as template also needs Admin on Settings, because it adds to the company's schedule templates.

Editing on the chart also needs two things that aren't about the person: your company must allow full control of schedules (Settings › Scheduling), and the project must be set to Full control. On a Read only project, nobody edits the chart; it changes by importing again.

Standard roles

Role Schedule access
Internal - Super Admin Edit / Import Schedules
Internal - Project Admin Edit / Import Schedules
Internal - Project Manager Edit / Import Schedules
Internal - General Superintendent Edit / Import Schedules
Internal - Superintendent Edit / Import Schedules
Internal - Field Engineer Read
Internal - Contract Admin/Accounting Read
Internal - Read Only Read
External - Architect, External - Engineer, External - Subcontractor, External - Owners Rep, Internal - Organization Admin, Internal - Directory Read, Internal - Directory Admin None

Your company may already have changed these, or added its own roles.

What people without access see

  • With no schedule access, Schedule doesn't appear in the project sidebar, and the dashboard's schedule cards aren't shown. Opening a link to the schedule shows that they don't have access.
  • With Read, the chart has no editing toolbar, and Schedule settings, Import schedule and Switch to full control aren't shown. A project with no schedule just says "No schedule has been imported for this project."
  • If your company has switched the Schedule module off for its projects, Schedule is hidden from the sidebar for everyone.
  • With Edit but not Edit / Import Schedules, the editing toolbar appears on a project with full control, but the import, settings and history controls don't.