The history is at the bottom of the Import schedule panel. It's called Previous imports, or History once the project has versions edited in StruXure. The newest is at the top, and the one the project shows now is marked Current.

Each row shows:
- File: the file's name and size, or for a version edited here, what it is: Built in StruXure, Edited in StruXure from a file, or Restored from a file.
- When: when it was imported or made, and by whom. A version edited here also shows when it was last saved, and by whom.
- Outcome: how many activities and dependencies it has (and, for a version edited here, how many saves), or why a failed import couldn't be read.
Restore a version
- Open the project's Schedule and click Import schedule.
- In the history, find the version you want and click Restore.
A green line at the top of the panel confirms which version was restored. The Gantt chart, calendar, milestones and the dashboard's schedule cards all show it straight away.
If RFIs, submittals or change events name activities that the restored version doesn't have, a box under the green line lists them so you can pick their activities again. See Import a schedule.
On a project with full control, restoring makes a new working copy of that version, so the version itself stays as it was. Your next edits go into the copy.
Download an imported file
Click a file's name to download it exactly as it was uploaded, for example to open an earlier version in Microsoft Project.
Remove an entry
- Click Remove on the row. You can't remove the current one.
- Confirm in the dialog.
- Removing an import removes the uploaded file and its line in the list. Use it to clear away a failed or mistaken upload.
- Removing a version edited in StruXure removes that version and every task in it from the history. The current schedule isn't affected.
Removing an entry can't be undone, and the schedule has no recycle bin. If you might need a version again, leave it in the history.