See proposed delays on the schedule

Which activities open RFIs, submittals and change events expect to delay, and what the schedule would look like if those delays happened.

Who this is forProject managers, Schedulers, Superintendents

Permission neededSchedule — Read

An RFI, a submittal or a change event can say which activities in the schedule it is expected to hold up, and by how many working days. The schedule shows those proposed delays without changing anything in it.

Say what a record delays

  • RFI: in the column on the right, under Schedule impact?, click Affected activities. Pick an activity and enter its working days. Click Add activity for another, then Save. See Edit an RFI's details.
  • Change event: the same, under Affected activities in its Details card, while it's a Draft. See Change events.
  • Submittal: pick its Schedule activity, then enter the days under Expected delay. See Edit a submittal's details.

Each activity has its own days, so one RFI can hold up one activity by five days and another by two.

See them on the Gantt chart

On the Gantt tab, an activity that open records expect to delay has an amber tag before its name, such as +5d. Point at the tag, or at the bar, to see each record and its days.

To open one of those records, click the tag: a list shows each record with its days, and clicking one opens it. You can also right-click the activity's row or bar and choose Go to and the record. On a schedule you're editing, the Go to items are at the top of the right-click menu.

Under the chart, Proposed delays from open records lists every one: the activity, the record and the working days. Click the activity to find it on the chart, or the record to open it.

Only open records count. An RFI or submittal that is closed or cancelled, a change event that is void, and anything in the recycle bin are left out.

See the projected schedule

Above the chart, click Projected. The chart shows the schedule as if the proposed delays happened:

  • A delayed activity moves later by its days, counted on the project's working days, so a delay over a weekend lands after it.
  • Activities that depend on it move only as far as they have to. If there was already a gap between them, the gap takes up the delay first.
  • A moved bar is striped, and a thin grey line under it shows where it is in the schedule now. Point at it to see how many working days later it is.
  • Critical Path shows the critical path through the projected dates.
  • If two records delay the same activity, the larger delay is used, not the two added together.

The line beside the switch says where the schedule would now finish and how many working days later that is, or that the delays don't move the finish.

Nothing in the schedule changes. Click As scheduled to go back. While Projected is showing, the schedule can't be edited.

Print and Export CSV at the top of the page give you the view that's showing. With Projected selected:

  • Print opens a PDF titled Projected Schedule, with the projected dates and a line saying where the schedule would now finish, how many working days later that is, and how many activities moved.
  • Export CSV downloads a file whose name ends in projected, with the projected dates and a last column, Moved (working days), for each activity.

With As scheduled selected they give the schedule as it is. To compare the two side by side, print once in each view.

Note

The switch only appears when an open record expects a delay to an activity in the current schedule.