Financials is an add-on. If your company has it, each project's menu has a Financials group, and Changes in it opens the project's changes: anything that may change the cost of the job or the contract. The page has three tabs, Change Events, Prime Change Orders and Commitment Change Orders. This article is about the first.
Across the top are four totals. Click one to open the tab it counts:
- Being priced: owner changes and allowances not yet approved, at their price now, and how many are waiting for approval.
- Ready for a change order: approved potential change orders not yet on a Prime Change Order.
- With the owner: Prime Change Orders sent to the owner.
- Approved by the owner: what the owner has approved and added to the contract.
The Change Events tab lists each change event with its number, its PCO number once it has one, its type, status, days, cost and price. Use Columns to choose what shows, click a heading to sort, and search or filter the list. Click a number or title to open it.
If your company has renamed "Change Event" or "Potential Change Order" under Settings → Financials, the pages use your words.
Types
| Type | What it becomes |
|---|---|
| Owner change | A potential change order, priced with markups and bond. |
| Allowance | A potential change order, priced the same way. |
| Contingency draw | Cost only. |
| Internal | Cost only. |
| Work order | Cost only. |
| Back charge | Cost only. |
Once a change event is approved, a commitment change order or back charge can take it up, and copy its lines onto the vendor's commitment at their cost. See Change a commitment and charge costs back to a vendor.
Create a change event
With Financials — Edit:
- Click New change event at the top of the Changes page.
- Choose the Type and type a Title.
- If you know them, fill in the Details panel on the right: Came from and Description on What, Days and Bond % on Impact. You can change them later.
- Click Create change event.
It is made as a Draft and opens on its own page, with Add a line open. Its number, such as 001, is given now and never changes.
Its page
At the top right of the change event's page are PDF, and Add to a change order when you may. Take back to Draft and Void are in the ⋯ menu beside them.
Under the title, the approval card says where it stands and what happens next, with its buttons: Send for approval on a Draft, or Approve and Return when it is your turn. The card shows its whole life, left to right: Draft, Sent for approval, each step of its route (on a Draft, the steps its route has at its amount now), then Approved. Each stage it has reached says who took it there and when, the one it is in is marked as current, and a step still to decide says who it waits on. A returned one says on Draft who returned it and why; a void one ends at Void, with who voided it. Once there is nothing left to do on it, the card closes to one line; click Show steps to open it.
Two cards are below it:
- Details: what it is.
- Beside it, the amount, large. On an owner change or allowance it is the Potential Change Order amount, made up of Cost, Overhead, Profit and the bond; on any other type it is the Cost. Below are its number of Lines and Days, and its PCO and Prime Change Order once it has them.
Its Lines are below them.
Fill in its details
On a Draft, with Financials — Edit, click a value in the Details card to change it. It saves when you finish. The details are:
- Title and Type.
- Came from: the RFIs, submittals and observations on this project that raised it. Pick them from the list.
- Days: what it does to the schedule, in whole days. Use a minus sign for days saved.
- Affected activities: the activities in the project schedule it is expected to hold up, each with its number of working days. Pick an activity and enter its days; click Add activity for another row, or the X beside a row to remove it, then Save. The schedule shows these as proposed delays. See See proposed delays on the schedule. Shown if you can see the project's schedule.
- Bond, on an owner change or allowance: starts at your company's bond. See Set the markups a change is priced with.
- Description.
Once it is sent for approval, its details are shown as text.
Price its lines
On a Draft, click Add line above the lines. Under Add a line, enter:
- Cost code and Cost type.
- Description.
- Done by: Our own forces or Subcontractor.
- Cost: a credit is written with a minus sign or in brackets.
- On an owner change or allowance, Overhead % and Profit %. Type a percentage, or leave a box empty to use your company's markup for who does the work. The line under the boxes says what those are. If your company has none set, an empty box adds nothing. See Set the markups a change is priced with.
Click Add line. The form stays open for the next line; click Close when you're done.
To change a line, click the pencil in its Actions column, change it, and click Save. To remove one, click the trash can, then Delete. Its history is kept.
On a project whose Prime Contract is Unit price, an owner change's or allowance's lines are items instead: a New item, a Quantity change or a Unit price change. See Change a unit-price contract.
The lines show each line's cost and, on an owner change or allowance, its overhead, profit, markup and the line with markup, with a Total row. A line's markup is its cost times its overhead and profit; the bond is the cost and markup times the bond.
Price it by force account
On a Draft, the Force account card lists the worksheets that price extra work from crew and equipment hours, and New force account starts one. See Price extra work by force account.
Send it for approval
When it has at least one line, click Send for approval on the approval card. Until then the card says what to do first. It goes through your company's approval route for Change Events, or the project's own: by default, one approval from anyone with Financials — Approve on the project. See Set who approves financial documents. If no step of the route applies at its amount, the button reads Submit and it is approved as it is sent.
It is Waiting for approval, and its details and lines can't be changed. To change it, click ⋯, then Take back to Draft.
When it is your turn on its route, the card shows Approve and Return. Approve moves it to the route's next step, or approves it on the last. Return asks why it is returned; returned, it is a Draft again, and the card shows the reason. It also appears on the project's Approvals page while it waits.
Approved, it is settled. An owner change or allowance is given its PCO number, such as PCO-001, which never changes. The amount card then names the Prime Change Order it is on. If it isn't on one yet, with Financials — Edit click Add to a change order at the top right to start a new Prime Change Order with it ticked. See Put changes to the owner with a Prime Change Order.
Download it as a PDF
Click PDF at the top right of the page. See Download a change event as a PDF.
Void a change event
A Draft can be voided with Financials — Edit, and one waiting for approval with Financials — Approve. Click ⋯ at the top right, then Void, and Void again. It keeps its number and its history. An approved change event isn't voided.
History
With Financials — Approve, click History at the top of the page. It opens the Financials audit for this change event and its lines: who changed what, when, and the value before and after.