Enter and review a unit-price sub invoice by quantity

On a unit-price commitment, enter the quantity a sub installed on each item this period with its backup, approve less than the sub claimed, and see what is due, held and sent to accounting.

Who this is forProject managers, Project assistants, Contract administrators, Accounting

Permission neededFinancials — Read to see it, Edit to enter quantities and backup, Approve on the step whose turn it is to review it

On a Unit price commitment, a sub invoice bills each item by the quantity the sub installed, not by an amount. You start it, enter its details, send it for review, take it back and void it the same way as on a lump-sum commitment: see Enter a sub invoice.

For the commitment's items themselves, see Price lines by quantity on a unit-price contract.

How an item's amount is worked out

Each item's Amount to date is its quantity to date × its unit price, rounded to the cent. What it bills this period is that amount less what the sub invoices before it billed. So the amount to date always matches the quantity to date, however the cents fell on earlier invoices.

For example, 815 LF of pipe at $193.70 is $157,865.50. Billed 500 LF in August and 315 LF in September, it bills $96,850.00 and then $61,015.50: 815 LF and $157,865.50 to date.

A sub invoice for a commitment change order bills that change order's items the same way. A quantity change bills at its item's unit price; a unit price change bills at the difference between the new unit price and the old.

The lines

On a unit-price commitment, the Lines grid shows:

Column What it is
Item The bid item number.
Description What the item is for. Lump sum shows beside a lump-sum item, and Overrun beside an item billed past its quantity.
Unit What its quantity is measured in.
Contract qty Its quantity on the commitment or change order.
Unit price Its price for one unit.
Value Contract qty × unit price.
Qty previous What the sub invoices before this one billed, at what was approved on them.
Qty this period What the sub billed this period.
Approved qty Once it is sent for review: what this period counts.
Qty to date Previous and this period's quantity together.
Amount to date Qty to date × unit price, rounded to the cent.
Stored materials Materials on hand and not yet in the work, as of this invoice.
% complete Qty to date over its contract qty.
Balance to finish Its value less what is completed and stored to date.
Backup How many backup entries the item has.

An item can be billed past its quantity: the commitment pays for what is installed. It is marked Overrun, with what is billed under it, and the sub invoice can still be sent for review. An approved change order that adds to the item's quantity counts with it, so an item its change order covers isn't marked. See Find and settle overruns on a unit-price contract. A quantity to date below nothing is marked Billed below nothing., and the sub invoice can't be sent until it is corrected.

Enter an item

With Financials — Edit, on a Draft, click the pencil (Enter) in the item's Actions column, then:

  1. Type the Quantity this period. A quantity can be below nothing, to take back one billed before. For a lump-sum item, such as Mobilization, type its % complete to date instead. It is billed as that share of its quantity: 30% of 1 EA is 0.3.
  2. Type Stored materials, if any.
  3. Click Save.

Add the backup

To keep where each quantity was installed, with Financials — Edit:

  1. Open the item with its pencil. Under Backup, click Add backup entry.
  2. Type the Quantity installed, and if you like the day it was Installed on, the Location, the Station from and Station to, and choose the Plan sheet from the project's drawings.
  3. Click Add.

Once an item has backup entries, it bills their total: you change its quantity by changing them. Click the pencil (Change) on an entry to edit it and click Save, or Remove and Remove again to take it off. Backup can be changed only while the sub invoice is a Draft. Past Draft, anyone who can see the sub invoice can open an item to read its backup.

Approve less than the sub claimed

When it is your turn to review it (see Review and approve a sub invoice):

  1. Click the pencil (Review) in the item's Actions column.
  2. Change Approved qty, and Approved stored materials if you need to.
  3. Type a Note saying why.
  4. Click Approve as noted.

The approved amount follows the quantity: 500 LF approved of 520 LF claimed, at $193.70, is $96,850.00. Amount to date, % complete, Balance to finish and the totals under the items follow what is approved. An item can't be approved at more than the sub claimed on it, or below nothing to date.

Items you don't note are approved as billed when you approve the sub invoice. Later sub invoices start from the quantity approved, not the quantity claimed.

What is due, and what goes to accounting

Totals shows what was approved this period, the retainage held on it and what is due, the same as on any sub invoice. The net sheet's Due and what goes to accounting are those approved amounts. If your accounting system takes quantities, each item's approved quantity, unit and unit price go too. See Pay suppliers by joint check with a net sheet and Send a sub invoice to accounting.