Financials is an add-on. If your company has it, the Financials group on each project's menu has Closeout. You can also open it from Closeout at the top right of the Financials Overview.

The checklist

Each item says where it stands, Done or Open, with a link to the page where you act on it. The top of the page counts how many are done.

Item Done when
Final pay application or retainage release paid A retainage release is paid and nothing is still held, or the last pay application holds no retainage and is paid. Otherwise it says what is held, or where the release stands.
Final lien waiver from every commitment Each commitment past approval has its sub's unconditional final release received, accepted or waived.
Every vendor’s compliance current Every vendor on the project is clear to pay.
No open change events or PCOs No change event is in Draft or waiting for approval, every approved PCO is on a change order, and no prime change order is waiting on the owner.
Punch list items all closed No punch item is open.
RFIs all closed No RFI is in Draft or open.
Submittals all closed No submittal is open.

Under each open item, Still open names up to five of what is left. Punch list, RFI and submittal items show only to people who can see those modules.

To collect

Warranties and O&M manuals aren't records in StruXure. They are listed as To collect, with a link to the project's Files, where you keep them.

Download the closeout package

Click Download closeout package at the top right. It downloads a ZIP of what StruXure holds for the job:

  • 00 Index.pdf and 00 Index.csv: every document in the package, and the prime change orders, with each one's status.
  • 01 Prime contract: the signed Prime Contract.
  • 02 Pay Applications: each submitted, posted or paid pay application's application for payment and continuation sheet.
  • 03 Change events: each change event's PDF, other than a Draft or a void one.
  • 04 Lien waivers: each signed release copy held on a sub invoice.

Each document in the package is recorded as downloaded by you, on its own history.