Build, check and lock the Original Estimate

Import a project's estimate or start one by hand, change its lines while it is a draft, and lock it as the Original Estimate.

Who this is forProject managers, Project executives, Accounting

Permission neededFinancials — Read to see it, Edit to change and lock it, Approve to unlock it

Financials is an add-on. If your company has it, each project's menu has a Financials group, and Estimate in it is the project's estimate. Once it is locked it becomes the project's Original Estimate: the budget and the Buyout Log are built from it, and later changes are measured against it.

If your company has renamed "Estimate" under Settings → Financials, the page uses your word.

Start the estimate

Open the project and choose Estimate under Financials in the sidebar. If the project has none yet, the page says so and offers two ways to start:

  • Import from a file: bring in a spreadsheet (see Import an estimate from a file).
  • Start from scratch: start an empty draft and add its lines by hand.

Read it

Across the top are the totals: Work, General conditions and Total, and, if the estimate splits lines across allocation buckets (for example Cap 1 or Rx Exp), each bucket's total and Not allocated.

The lines are a grid with tabs for Work and General conditions, a search box, filters and Columns, and the money totalled at the foot. Columns you can show include Line, Trade or scope, Section, Cost code, Cost type, Quantity, Unit, Unit price, Amount, Bids, Low bid, Carried bid and Notes. Hover Bids to see each sub bid, which were qualified and which one the line was priced from.

Each line shows its cost code with the code's description beside it, and its cost type's number with the type's name in a coloured tag: one colour each for labor, material, subcontract and equipment, and grey for any other type. A unit price shows its unit after it, for example /SY. The foot reads Total and how many lines it adds up, or Total shown when a search or filter narrows them; it stays in view while the lines scroll.

CSV and PDF Report above the grid download the lines as they're showing (see Export a Financials list to CSV or PDF).

Change it while it is a draft

Until it is locked, its badge says Draft and its lines can change:

  1. To add one, click Add line, fill it in and save.
  2. To change one, click the pencil in its Actions column; its form opens beneath it.
  3. To take one off, open it and click Remove, then confirm.

Import again replaces the whole draft from a file.

Lock it as the Original Estimate

  1. Check the lines and the totals.
  2. If the page shows Before it can be locked, fix each line it lists. Every line with an amount needs a cost code and a cost type from your company's lists. Add a missing one under Settings → Financials, then reopen the page: the line matches without importing again.
  3. Click Lock, then Lock in the dialog.

Its title becomes Original Estimate and its badge Locked.

Unlock it

Someone with Financials — Approve can click Unlock on a locked estimate, while nothing has been built from it yet. It becomes a draft again, its lines can be changed or imported again, and it has to be locked again before the budget is built.

Who can do what

  • With Financials — Read on the project, you can open the estimate.
  • With Financials — Edit, you can start, import, change and lock it.
  • With Financials — Approve, you can also unlock it, and History opens the Financials audit filtered to the estimate.