Start a unit-price job part-way with an opening balance

For a unit-price job brought into StruXure mid-contract, enter or import what each item billed the owner before, so the first pay application bills on from it.

Who this is forProject managers, Project executives, Project assistants, Accounting

Permission neededFinancials — Read to see it, Edit to enter and import it, Approve to see its history

When a job comes into StruXure after the owner has already been billed, you enter what each item billed to date as an opening balance. It isn't a pay application: StruXure's pay applications start at 1, and the first one's previous columns start from the opening balance.

Opening balances are for a Unit price Prime Contract. A lump-sum contract has none.

Open it

  1. On the project, open Pay Applications.
  2. In the Opening balance card, click Enter opening balance. Once something is entered, the card shows what it comes to, and the link reads Open.

The card shows only to people who can enter it, or once there is an opening balance to see. If a pay application was submitted before anything was entered, there is none, and the job bills on from that application.

Enter the day and the retainage

At the top, enter:

  • Billed through: the last day the owner was billed for before StruXure. The first pay application's period must end after it.
  • Retainage held %: the retainage the owner held on what was billed.

Click Save. The card shows Billed to date, the retainage held, and Previous certificates for payment: what was billed less the retainage. That is line 7 of the first pay application.

Enter an item

Each item of the schedule of values is listed, grouped by section if the contract has them. For an item:

  1. Click Enter under it.
  2. Enter its Quantity to date. For a lump-sum item, such as Mobilization, enter its % complete to date instead: 30% of 1 EA is 0.3.
  3. Leave Amount to date empty to bill the quantity × unit price. If the owner certified another figure, enter it.
  4. Click Save.

If an amount differs from the quantity × unit price, the item says by how much. The first pay application evens it: its amount to date is always its quantity to date × unit price, so it bills the difference.

Import it from a spreadsheet

You can fill every item at once from a .csv or .xlsx:

  • a header row with an Item column and a Quantity or Amount column (Qty to date and Amount to date work too),
  • one row for each item billed to date, with its item number as on the schedule of values.

An amount left empty is the quantity × unit price. Rows with no item number are skipped. Under Import, choose the file and click Import.

If a row can't be read, such as an item number that isn't on the schedule of values, one that is in the sheet twice, or a quantity that isn't a number, nothing is imported and each problem names its row. Items the sheet leaves out keep what they have.

When it locks

You can change the opening balance until the first pay application is submitted. Submitting it locks the opening balance, and it no longer changes, even if that pay application is reopened. The page then says Locked when the first Pay Application was submitted.

If you change the opening balance while a pay application is in Draft, the Draft's figures follow it, and any approval given on the Draft is taken back.

History

People with Financials Approve see the opening balance's History: when it was started, each change to the day, the retainage and what it comes to, each item's quantity and amount before and after, and when it was locked.