A retainage release is a pay application whose purpose is paying out the retainage the owner has held. It bills no new work. Its retainage percentages are lowered, so its Current payment due is the retainage released.
If your company has renamed "Pay Application" or "Retainage" under Settings → Financials, the pages use your words.
Request one
With Financials — Edit:
- Open Pay Applications, or the latest submitted, posted or paid pay application.
- Under Request retainage release, choose how much:
- All of it
- A percentage of what is held, such as 50
- An amount, in dollars
- Click Request release.
It opens as a Draft, numbered the project's next, with Retainage release after its number. Its application date is today, and so is its period ending when that is after the last one's.
Request retainage release shows when the latest submitted, posted or paid pay application holds retainage and no pay application is a Draft. The card says how much is held, and after which pay application.
What it releases
Its retainage percentages start from the last pay application's:
- All of it sets both to 0%.
- A percentage lowers both by that share: releasing 50% of 5% holds 2.5%.
- An amount lowers both by the share the amount is of what is held. A percentage is kept to four decimal places, so the release is the nearest it can come to the amount, within a few cents.
Beside the sheet, Retainage release shows what was Held before, what it Released and what is Still held. On the Application for payment, line 5 is what is still held, and line 8, Current payment due, is the release.
You can still change its details or enter work on a line, like any Draft.
Send it
It goes to the owner the same way as any pay application: its approval route, then accounting, then the owner's payment. See Send a pay application for approval and submit it.
Its PDF is titled with Retainage release, and shows the retainage held before and released.