Put changes to the owner with a Prime Change Order

Bundle approved potential change orders into a Prime Change Order, send it for approval, record the owner's approval or denial, step a denial back, revise or void it, and see what it does to the contract sum and the schedule of values.

Who this is forProject managers, Project executives, Contract administrators, Accounting

Permission neededFinancials — Read to see them, Edit to make, change, send, take back and revise one, Approve to approve or return it, record the owner's answer, step a denied one back, void one past Draft and see the history; Accounting — Work accounting to send one to accounting

Financials is an add-on. If your company has it, each project's menu has a Financials group. Click Changes in it, then the Prime Change Orders tab, to see the project's Prime Change Orders: the changes to the contract with the owner.

A Prime Change Order bundles potential change orders (PCOs): owner changes and allowances that have been priced and approved on the Change Events tab. See Record a change and price it.

Change orders change the project's Prime Contract, so there are none until it has been started; until then the tab links to the Prime Contract. If your company has renamed "Prime Change Order", "Potential Change Order" or "Prime Contract" under Settings → Financials, the pages use your words.

On a Unit price Prime Contract, a change order names the section it is for, and the owner's approval adds its items to the schedule of values or changes the items there. See Change a unit-price contract.

The Prime Change Orders tab

The four totals across the top of the Changes page show Ready for a change order (approved PCOs not on one yet), With the owner and Approved by the owner.

The list shows every change order with its Number, Title, Status, how many PCOs it has, its Days, its Amount and the day of the Owner’s answer, with a tab for each status. Use Columns to add With the owner, Revision or To the owner. Click a number or title to open one.

Below the list, a card lists the approved PCOs that aren't on a change order yet, and what they come to.

Make one

With Financials — Edit:

  1. Click New prime change order at the top of the Changes page.
  2. Type a Title.
  3. Under Approved potential change orders to include, tick the PCOs it bundles. The total of those ticked shows as you tick.
  4. If you like, open the Details panel on the right: type a Description on What, or Days on Impact. Leave Days empty to take the days from its potential change orders.
  5. Click Create prime change order.

It opens as a Draft, numbered the project's next. From an approved PCO's page, Add to a change order opens this page with that PCO ticked.

On a Draft, click a value under Details to change it: Title, Days or Description. It saves when you finish.

To change the PCOs it bundles, click Add PCOs on the Potential Change Orders card. It lists the PCOs on this change order, ticked, and the approved PCOs that aren't on another change order, each with its Title, Type, Days and Price. Tick the ones it bundles, untick any to take off, and click Save. A PCO is on one change order at a time; a void change order lets its PCOs go.

Its amount is what its PCOs are priced at. The Potential Change Orders card lists each with its type, title, days and price, and shows the Amount.

Send it for approval

Click Send for approval. If nothing on its approval route applies at its amount, the button is Submit instead, and it is approved as soon as you click it. Until it can go, the page says why: it needs at least one PCO, and the Prime Contract must be executed.

It goes through the project's approval route for Prime Change Orders, at its amount (a credit counts at its size). The card at the top of the page shows its whole life, left to right: Draft, Sent for approval, each step of its route, With the owner, then Approved by the owner or Denied by the owner. Each stage it has reached says who took it there and when, the one it is in is marked as current, and those still to come follow it. A void one ends at Void, with who voided it. Once there is nothing left to do on it, the card closes to one line, with Accounting beside it; click Show steps to open it. When it is your turn, it says Your approval is needed.: click Approve, or Return, which asks Why is it returned? Returned, it is a Draft again. While it waits, open the ⋯ menu at the top right and click Take back to Draft to change it again. See See and set who approves on a project.

Once approved, or at once if no step applies to its amount, it is With the owner.

Record the owner's answer

When the owner answers, someone with Financials — Approve fills in The owner’s answer:

  1. Choose Approved or Denied under Answer.
  2. Under On, enter the day the answer came. It can't be later than today.
  3. If you like, type who Signed for the owner by and a Note.
  4. Click Record, then Record again.

Approved, it can't be changed, voided or undone. To take it back, make another change order. It then:

  • adds its amount to the contract's Approved changes, and so to the Revised contract sum;
  • becomes a line on the schedule of values, at its amount;
  • goes to accounting, if your company sends Prime Change Orders when they are approved.

The Prime Contract card on the change order shows the Contract sum, Approved changes and Revised contract sum, and, before the owner approves it, the sum With this one.

Step a denied one back

If the owner's denial was recorded by mistake, someone with Financials — Approve can step it back to With the owner:

  1. On the card at the top of the page, click Step back to With the owner. If the card is closed to one line, click Show steps first.
  2. Under Why is it stepped back?, say why.
  3. Click Step back.

The owner's answer is cleared, and the owner's answer can be recorded again. With the owner says who stepped it back, when and why, and the change is in its history. One the owner approved isn't stepped back: it is in the contract, and another change order takes it back.

Revise or void one

  • Revise one that is with the owner, or denied: click Revise, then Revise again. It goes back to Draft as its next revision, keeping its PCOs, and the owner's answer is cleared. Its history keeps what each revision was.
  • Void a Draft with Financials — Edit, or one waiting for approval, with the owner or denied with Financials — Approve. Open the ⋯ menu at the top right, click Void, then Void again. It keeps its number and its history, and its PCOs can go on another change order.

Accounting

Each approved change order goes to accounting as its own record: its number, revision, title, amount, days and the day the owner approved it, with its PCOs as its lines. On a unit-price contract, if your accounting system takes quantities, its changes to the items go with it too: each new item, quantity change or unit price change, with its quantity, unit and unit price. Whether that happens when it is approved or only when someone sends it is set under Settings → Financials → Accounting. Where your accounting connection can't take it, it becomes a Manual Task.

The Accounting card, at the top, says where it stands: Not in accounting, On its way to accounting, Waiting for accounting to key it, In accounting with its ID, or Didn’t go through with the reason. Someone with Accounting — Work accounting can click Send to accounting on an approved one that hasn't gone yet, then Send. It reads Send again if its last send was cancelled.

Insights

If your company has Insights on, a change order that adds to the contract gets an Insight once it has been pending for more than 30 days since it was sent for approval. It says how long it has waited, what it comes to and its PCOs: until the owner approves it, that amount isn't in the Revised contract sum and can't be billed.

  • While it waits for approval, the Insight sits under Approval and is for whoever the approval is waiting on.
  • Once it is with the owner, it sits under The owner’s answer.

It goes away when the owner approves or denies it, or when it is taken back, revised or voided. Sent again, its 30 days start again. A credit doesn't get one. See Turn Insights on or off.

History

With Financials — Approve, click History at the top of the change order. It opens the Financials audit for it: its status, amount, PCOs, days, revision, the owner's answer, who did it and when.

Generate it as a document

The Change order document card makes it as a PDF from your company's template, or StruXure's built-in, and keeps each one made. See Generate a commitment's subcontract agreement.