Bill a unit-price contract by quantity

On a unit-price Prime Contract, enter the quantity installed on each item this period with its backup, read the continuation sheet by quantity, and print it whole or by section.

Who this is forProject managers, Project executives, Project assistants, Accounting

Permission neededFinancials — Read to see it, print it and download it, Edit to enter quantities and backup

On a Unit price Prime Contract, a pay application bills each item by the quantity installed, not by an amount. You start it, enter its details, send it for approval and reopen it the same way as on a lump-sum contract: see Bill the owner with a pay application.

For the items themselves, see Price lines by quantity on a unit-price contract.

How an item's amount is worked out

Each item's Amount to date is its quantity to date × its unit price, rounded to the cent. What it bills this period is that amount less what the pay applications before it billed. So the amount to date always matches the quantity to date, however the cents fell on earlier applications.

For example, an item at $0.6750 a foot billed 1 foot a month bills $0.68, then $0.67, then $0.68: $2.03 for 3 feet, as 3 × $0.6750 rounds to.

An item can be billed past its contract quantity: the contract pays for what is installed. It is marked Overrun, and the pay application can still be submitted. See Find and settle overruns on a unit-price contract.

The continuation sheet

On a unit-price contract, the Continuation sheet shows:

Column What it is
Item The bid item number.
Description What the item is for. Lump sum shows beside a lump-sum item, and Overrun beside an item billed past its contract quantity, with what is billed under it.
Unit What its quantity is measured in.
Contract qty Its quantity on the schedule of values.
Unit price Its price for one unit.
Scheduled value Its value: contract quantity × unit price.
Qty previous What the pay applications before this one billed, starting from the opening balance on a job brought in part-way.
Qty this period Installed this period.
Qty to date Previous and this period's quantity together.
Amount to date Qty to date × unit price, rounded to the cent.
Stored materials On the MOH Materials on hand line after the items, the materials on hand as of this application. See Keep materials on hand on a unit-price pay application.
% Qty to date over its contract qty.
Balance to finish Its scheduled value less what is completed and stored to date.
Retainage This item's share of the retainage held to date.

On a contract with sections, a Section column shows each item's section. The sheet has a Total row; use Columns to choose what shows.

Above the sheet, the card says how many items are billed past their contract quantity, if any.

Enter an item

With Financials — Edit, on a Draft, click the pencil (Enter) in the item's Actions column, then:

  1. Type the Quantity this period. A quantity can be below nothing, to take back one billed before. For a lump-sum item, such as Mobilization, type its % complete to date instead. It is billed as that share of its quantity: 30% of 1 EA is 0.3.
  2. Click Save.

Materials on hand are kept apart, each at its invoice cost: see Keep materials on hand on a unit-price pay application. An item that still has an amount in Stored materials from before also shows Stored materials here, so you can clear it.

A unit-price item can't be filled in from approved sub invoices.

Add the backup

Owners often ask where each quantity was installed. With Financials — Edit:

  1. Open the item with its pencil. Click Backup, then Add a backup entry.
  2. Type the Quantity installed, and if you like the day it was Installed on, the Location, the Station from and Station to, and choose the Plan sheet from the project's drawings.
  3. Click Add.

Once an item has backup entries, it bills their total: its Quantity this period is set by them, and you change it by changing them. Click Change and the entry's quantity to edit it and click Save, or Remove and Remove again to take it off. Backup can be changed only while the pay application is a Draft. Afterwards, an item's pencil (Backup) opens the entries it was billed from.

Bring the period in from a tracking sheet

On a Draft, Import quantities at the top right of the continuation sheet fills the quantities and installs from the coordinator's tracking sheet, after a preview. It shows only once your company has an installed quantities import profile. See Import installed quantities into a pay application.

What must hold first

On a unit-price contract, one more thing must hold before either approval is given: Each item’s amount to date is its quantity to date × unit price. If it doesn't, it shows under Fix this first, naming any item whose amount doesn't match.

Sections

On a contract with sections, the Sections card shows what the pay application bills each one: its Authorized amount, Scheduled value, This period, Completed and stored to date, Retainage and what is Due. The sections come to the whole pay application. A section billed past its authorized amount says so under its name.

Click PDF beside a section to print it alone, for that section's owner or payer.

Click PDF at the top right of its page. On a unit-price contract, the continuation sheet has the columns above. A section's PDF has the section's figures in place of the application for payment, and its items alone on the continuation sheet.

When it reaches accounting

A unit-price pay application goes to your accounting system as a receivable invoice, as any pay application does. If your accounting system takes quantities, each item goes with its quantity this period, its unit and its unit price, beside the amount they bill. If it doesn't, the amounts go as they do on a lump-sum contract, and the quantities stay in StruXure.

In Sections, PrimeLink (CSV) beside each section downloads its items in PrimeLink's columns: Ref ID, Item, Description, UOM, Unit Price, Auth Qty, Qty This Period, Dollars This Period, Qty To Date and Dollars To Date, ready to copy into the payment request.