Keep materials on hand on a unit-price pay application

On a unit-price Prime Contract, add each material delivered and stored at its invoice cost, for the item it will go into, draw it down as it is installed, and choose whether retainage is held on it.

Who this is forProject managers, Project executives, Project assistants, Accounting

Permission neededFinancials — Read to see them, Edit to add, change and draw them down and to choose the retainage, Approve to see their history

On a Unit price Prime Contract, materials delivered to the job and stored, but not yet installed, are kept one material at a time under Materials on hand on each pay application. Each has its own unit and its unit cost: what the supplier's invoice charged, not the bid price. As the material is installed, you draw it down.

The continuation sheet shows all of them as one line, MOH Materials on hand, in the Stored materials column, as Spectrum's G703 does. A lump-sum contract has no Materials on hand card: its stored materials are typed on each line. See Bill the owner with a pay application.

Add a material

With Financials — Edit, on a pay application in Draft:

  1. Under Materials on hand, click Add a material.
  2. Type its Description, such as 12" PVC pipe.
  3. Under For item, choose the item of the schedule of values it will go into.
  4. Choose its Unit. It may differ from the item's: fabric stored in SY for an item measured in SF.
  5. Type the Unit cost from the invoice, to four decimal places.
  6. Type the Quantity this period stored, if any.
  7. Click Add.

Enter this period's quantity

Each material on hand is listed with:

Column What it is
Item The item it is for.
Description What it is. Open shows beside one that no submitted pay application has billed yet.
Unit and Unit cost What its quantity is measured in, and the invoice cost of one.
Qty previous On hand after the pay applications before this one.
Qty this period Stored this period, or drawn down when below nothing.
Qty on hand Previous and this period's quantity together.
This period What this period's quantity comes to.
On hand to date Qty on hand × unit cost, rounded to the cent.
Retainage Its share of the retainage held on stored materials.

To change this period's quantity, click Enter under the material, type the Quantity this period and click Save.

When material is installed, bill the item it went into by its quantity as usual, and draw the material down with a quantity below nothing. For example, 110 LF of pipe installed at $24.84 a foot is −110, and this period shows ($2,732.40). A material left alone keeps what is on hand. A period's amount, and what is on hand, can be below nothing; they are shown in parentheses.

Change or remove a material

Until a submitted pay application has billed it, a material is Open. Click Change under it to correct its description, item, unit or unit cost, and click Save, or click Remove to take it off the contract.

Once a pay application with a quantity for it is submitted, it is billed and keeps what it was billed at, even if that pay application is reopened. Draw it down to nothing instead.

Retainage on stored materials

The Prime Contract says whether retainage is held on stored materials. On a unit-price Prime Contract, the Billing card has Stored materials:

  • Held on stored materials: each pay application holds its Retainage on stored on them, line 5b. A new one starts it at the contract's retention.
  • Not held on stored materials: none is held on them, and the pay application's Application for payment says No retainage on stored materials.

Someone with Financials — Edit clicks Stored materials and chooses one. It saves when chosen. A pay application in Draft follows at once, and any approval given on it is taken back. Submitted pay applications keep what they held.

On the application for payment, the PDF and in accounting

Materials on hand count in Total completed and stored to date, line 4, and the retainage on stored materials, line 5b. On a contract with sections, each material counts in its item's section. The PDF prints them as the one Materials on hand line, and accounting gets them as one line too.

History

People with Financials — Approve click History at the top of the pay application to see, in its audit, each material's quantity before and after, and when each was added, changed, removed or billed.