Find and settle overruns on a unit-price contract

An item billed past its contract quantity is marked Overrun, and a section billed past its authorized amount is marked too. Make balancing change order drafts the change order that sets the items to what was installed.

Who this is forProject managers, Project executives, Accounting

Permission neededFinancials — Read to see overruns; Edit to make a commitment's balancing change order; Edit and Approve to make the Prime Contract's

On a Unit price contract, quantities are estimates and the contract pays for what is installed. So an item can be billed past its contract quantity. StruXure never refuses it: it marks it, so you can see it, check it and settle it.

On a Lump sum contract nothing changes: a line billed beyond its value is still refused before the pay application goes to the owner.

Where an overrun shows

An item whose quantity billed to date is past its contract quantity is marked Overrun:

Where What you see
Schedule of Values (on the Prime Contract page) Overrun beside the item, and under it what is billed, for example "35.88 EA billed of 4 EA (897%)". Above the grid, how many items are billed past their contract quantity. The Qty billed to date column shows each item's quantity billed, in amber when it is past.
Pay application Overrun beside the item on the Continuation sheet, and under it what is billed. It counts the quantity on this pay application, before it is submitted.
Sub invoice Overrun beside the item. An approved change order that adds to the item's quantity counts with it.
Commitment Overrun beside the item on its Schedule of values, and what is billed on its sub invoices.
Financials Overview Items overrun on the Schedule of Values card.

The Schedule of Values, the commitment and the Overview count what is billed on pay applications or sub invoices that have been submitted. The pay application and sub invoice pages count their own quantities too, so a mistake shows before it goes out.

The mark also catches keying errors. A block of quantities entered against the wrong item numbers shows as an item billed many times its quantity.

A section past its authorized amount

On a contract with sections, a section whose amount billed to date is past its authorized amount is marked as well. That is where owners stop paying until a change order raises the authorized amount.

  • On the Schedule of Values, each section's heading shows what it is Billed to date, and how far past its authorized amount if it is. The Sections card shows it under Billed to date too.
  • On a pay application, the Sections card says it under the section's name.
  • The Financials Overview shows Sections past authorized.

Make a balancing change order on the Prime Contract

With Financials — Edit and Approve, on the Prime Contract page under the schedule of values, the Make balancing change order card drafts a Prime Change Order that sets each item's contract quantity to its quantity billed, at its unit price. Civil jobs close out this way.

The card shows, for each section, how many items each choice changes and what it comes to. Then:

  1. Under Items, choose Items overrun (each item billed past its quantity goes up to it) or Every item (close-out) (every item goes to its quantity billed, up or down; an item not billed yet goes to nothing).
  2. On a contract with sections, choose the Section. A change order is for one section.
  3. Choose the Cost type its lines are kept under. If an item has no cost code, choose the Cost code for items without one.
  4. Click Make balancing change order, then Make it.

It makes a Change Event with a quantity change for each item, approved at once as the project's next PCO, with no overhead, profit or bond. Then it opens a Draft Prime Change Order with that PCO in it, for the section you chose. It comes to the difference between what was billed and the contract amounts.

From there it goes for approval and to the owner as any change order does (see Put changes to the owner with a Prime Change Order). Nothing on the schedule of values changes until the owner approves it. Then each item's contract quantity becomes its quantity billed, and the section's authorized amount goes up by the change order's amount.

Make a balancing change order on a commitment

With Financials — Edit, on a unit-price commitment that has been approved, Make balancing change order… drafts a Commitment Change Order that sets each item's quantity to the quantity billed on its sub invoices.

  1. Open the ⋯ menu at the top right of the commitment and click Make balancing change order….
  2. Under Items, choose Items overrun or Every item (close-out). Each shows how many items it changes and what it comes to.
  3. Click Make it.

While items are billed past their quantity, the card at the top of the commitment says how many and what they come to, with a Make balancing change order button that raises just those items.

A Draft Commitment Change Order opens, with a quantity change for each item. It goes for approval as any other (see Change a commitment and charge costs back to a vendor).

The Insight

Where your company has Insights on, an item of a unit-price Prime Contract billed past its contract quantity on submitted pay applications raises an Insight on the Schedule of Values, under the item's description. It says how far past, and what that comes to at the item's unit price. It goes away once a change order sets the item's quantity, or the quantity is corrected.