Financials is an add-on. If your company has it, each project's menu has a Financials group. Open Prime Contract in it: the Schedule of Values is on that page, under the contract's details. It lists the lines the owner is billed against. They belong to the Prime Contract, and are separate from the budget.
If your company has renamed "Schedule of Values" under Settings → Financials, the page uses your word.
Until the project's Prime Contract has been started, there is no schedule of values. See Keep the Prime Contract and execute it.
This article is for a Lump sum Prime Contract. On a Unit price one, each line is a quantity at a unit price, and lines aren't split. See Price lines by quantity on a unit-price contract.
Read the lines
The grid shows each line's Item, Cost code, Scheduled value, Billed to date (billed on submitted, posted and paid pay applications) and Balance (its value less what is billed to date). Description is always shown; Parts can be added from Columns.
Use Columns to choose and order the columns, click a heading to sort, search, filter and save the view. The Total row at the foot adds up the lines showing. Click the Full screen icon beside Columns to give the grid the whole window; Esc exits.
If the lines don't come to the contract sum, a notice above the grid says by how much they are less or more. Once the owner has approved a Prime Change Order, the lines are compared with the revised contract sum.
Each Prime Change Order the owner approves adds a line at its amount, below nothing for a credit, linked to the change order. Its description and cost code can be changed, but not its value, and it can't be split or deleted: another change order changes it. Accounting gets it as the change order, not with the Prime Contract's schedule of values. See Put changes to the owner with a Prime Change Order.
Start from the budget
With Financials — Edit, while the schedule of values has no lines and the project has a budget:
- Click Start from the budget.
- Under Lines, choose One per cost code or One per budget line. Each line starts at its revised budget. Contingency lines are left off.
- If the contract sum is more than those lines, the difference is the fee, shown as Fee. Choose Spread across the lines or Its own line.
- Check the lines in the preview: each line's Item, Description, Cost code, Budget and Scheduled value, with their Total.
- Click Create, which shows how many lines it adds.
With the fee placed either way, the lines come to the contract sum. With no contract sum yet, each line is its budget; Enter it on the contract takes you to it. Each line can be changed afterwards.
Add lines
With Financials — Edit:
- Click Add line.
- Type the Description.
- Choose a Cost code from your company's list, or leave No cost code.
- Type the Scheduled value.
- Click Add line.
Lines are numbered 1, 2, 3 in their order.
Change, move or delete a line
Click the pencil in the line's Actions column. Its form opens beneath it:
- Change its Description, Cost code or Scheduled value and click Save.
- To delete it, click the trash can beside Save and confirm. A split line's parts go with it.
- Under Order, use the up and down arrows to move it.
Split a line
Split a line when the owner is billed for it in parts, for example sitework as grading and paving.
- Click the pencil in the line's Actions column, then Split. A line not split yet starts with two halves.
- Type each part's description and value. As you type, the form shows Left to split and what is left; click Fill the next part to put it in the next empty part. When the parts come to the line's value, it says Comes to and the value. Leave a row empty to skip it.
- Click Save split.
The line shows in bold, and each part shows under it as a row of its own, numbered 1.1, 1.2 and so on, with its own Billed to date and Balance. The line keeps its value; to change it, change its parts.
To change the parts later, open Split again: change a row, fill in a spare row to add a part, or empty a part's row to take it away. Join the parts back makes it one line again, at the same value.
If a line's parts stop coming to its value, a notice above the grid names the line.
What goes to accounting
When the Prime Contract goes to accounting, its schedule of values goes with it: each line with its item number, description, cost code and scheduled value. A split line goes as the one line; its parts stay in StruXure. On a unit-price contract, if your accounting system takes quantities, each item also goes with its quantity, unit and unit price; if it doesn't, the amounts go alone.
Changing the schedule of values after the Prime Contract has been sent lets the Accounting area send it again.
After execution
Once the Prime Contract is executed you can still change the lines. Each change keeps the old value in the history. While the Prime Contract is closed, its schedule of values can't be changed.
History
With Financials — Approve, History at the top of the Prime Contract page opens the Financials Audit, filtered to the Prime Contract and its lines: each line added, changed, split, joined back or removed, with its old and new value and who did it.
Who can do what
- Financials — Read on the project: see the schedule of values.
- Financials — Edit: start it from the budget, add, change, move, split and delete lines.
- Financials — Approve: see its history.