Price lines by quantity on a unit-price contract

On a unit-price Prime Contract or commitment, give each line its item number, owner item, quantity, unit and unit price; its value is worked out for you.

Who this is forProject managers, Project executives, Contract administrators

Permission neededFinancials — Read to see the lines, Edit to change them, Approve to see their history

A Prime Contract or a commitment is Lump sum or Unit price. On a unit-price one, each line of its schedule of values is an item: a quantity at a unit price, as on a civil bid form. A lump-sum one works as described in Build the schedule of values and split its lines and Create a commitment and build its schedule of values.

To choose the type, see Keep the Prime Contract and execute it or Create a commitment and build its schedule of values.

The Prime Contract's schedule of values is on the Prime Contract page, under its details. While a unit-price Prime Contract is a Draft, you can bring its items in all at once from the bid schedule your estimating system exports: click Import a bid schedule above the grid. See Import a bid schedule into the schedule of values.

What a line shows

On a unit-price contract, the lines show:

Column What it is
Item The bid item number, such as 1290. Two lines can't share one.
Owner item The owner's item number, such as 309.1. Optional, and several lines may share it.
Description What the line is for.
Cost code Its cost codes.
Section On a contract with sections, the section it is in.
Quantity Up to four decimal places.
Unit From your company's list of units. Lump sum shows beside it for a lump-sum item.
Unit price Up to four decimal places of a dollar.
Value The quantity × the unit price, rounded to the cent.
Qty billed to date The quantity pay applications have billed on it.
Billed to date and Balance What is billed on it, and its value less that.

For example, 3,065 LF at $0.6750 is worth $2,068.88, and 8.3 TON at $1.00 is worth $8.30. The Total row adds up the lines' values. Use Columns to show or hide columns.

A commitment's lines show their Item, Owner item, Cost code, Cost type, Description, Source, Quantity, Unit, Unit price, Billed to date and Value.

Add a line

With Financials — Edit, click Add line, then:

  1. Type the Description.
  2. Check the Item. It starts at the next number after the largest one on the contract.
  3. Type the Owner item and the Owner reference if the owner has them.
  4. Type the Quantity, choose the Unit and type the Unit price. A quantity of 0 is kept.
  5. Tick Lump sum for a lump-sum item inside the contract, such as Mobilization, even when its unit is EA.
  6. On the schedule of values, choose its Cost code and any Other cost codes: one item can be charged to several cost codes. The first is the one accounting gets with the Prime Contract. On a commitment, choose its Cost code and Cost type as on any line.
  7. On the schedule of values, if the contract has sections, choose its Section, or No section. See Divide a unit-price contract into sections.
  8. Click Add line.

On a commitment, a quantity may be below nothing, for a credit. A unit price never is.

The Unit list shows the units your company uses. A line keeps its unit even after your company retires it, but a new line can't take a retired unit. See Set contract types and units.

Change a line

Click the pencil in the line's Actions column. Its form opens beneath it. Change any of its boxes and click Save. The value is worked out again.

On the schedule of values, the trash can beside Save deletes the item, after you confirm. On a commitment, Remove line takes it off.

On a unit-price schedule of values, lines aren't split. The arrows under Order in a line's form move it up or down; on a contract with sections, among its own section's lines. A line an approved Prime Change Order added keeps its value: only its description and cost code change.

A commitment's lines change only while it is a Draft, as on a lump-sum one.

Switch a Draft's type

While the Prime Contract or commitment is a Draft, choosing the other type changes its lines too:

  • To Unit price: each line becomes 1 LS at its value, marked Lump sum, and is numbered by its place. A credit becomes −1 LS. If a line of the schedule of values is split, join its parts back first; until then, the switch is refused and says which line.
  • To Lump sum: each line keeps its value and drops its quantity, unit and unit price.

Lines taken from the Buyout Log onto a unit-price commitment come in as 1 LS at the scope's revised amount.

Codes for Spectrum

A unit-price Prime Contract's page has a Billing card with Spectrum company code, Spectrum customer code and Spectrum billing group: the codes Spectrum knows the contract by. With Financials — Edit, click one to change it. Each pay application's download for Spectrum carries them. See Bill a unit-price contract by quantity.

History

With Financials — Approve, History at the top of the Prime Contract or commitment page opens the Financials Audit: each change to a line's item, quantity, unit, unit price and value, with the old and new value. On the schedule of values, a line is named by its item number.

Related articles