On a Unit price Prime Contract or commitment, a change doesn't add an amount: it adds items, or changes the quantity or unit price of items already on the contract. A Lump sum contract's changes work as before. For how a unit-price contract's items are set up, see Price lines by quantity on a unit-price contract.
Three kinds of line
Each line is one of:
- New item: an item the contract doesn't have yet, with its Item number, Quantity, Unit and Unit price. Tick Lump sum for an item billed as a whole, such as a bond.
- Quantity change: more or less of an item already on the contract, at its unit price. Choose the Item from the list and type the Change in quantity, with a minus sign to take some off.
- Unit price change: a new unit price for an item already on the contract, for its whole quantity, such as when a quantity change triggers a repricing clause. Choose the Item and type the New unit price.
A quantity or unit price change is priced from the item as the contract has it when you save the line. Leave its Description empty to use the item's.
The Change column on each line says what it adds or changes, with its figures: "2 EA at $3,104.0229", "+100 LF at $0.675", "$85.00 → $90.00 on 1,200 LF".
Price a change event
On a project whose Prime Contract is Unit price, an Owner change or Allowance is priced in items. Its other types are cost only and take cost lines, as before.
On the change event's page, click Add line. Add a line has a form for each kind: New item, Quantity change and Unit price change; click one to open it. Each also has the Cost code, Cost type, Done by, Overhead % and Profit % of any line. Click Add line.
A line's cost is what its change comes to: a new item's quantity times its unit price, a quantity change times the item's unit price, or a unit price change's difference on the item's quantity. Overhead, profit and bond are added on that, as on any change. See Record a change and price it.
Put it to the owner
A Prime Change Order on a unit-price contract bundles its PCOs as before. See Put changes to the owner with a Prime Change Order.
If the contract has sections, click Section on the change order's Details card and choose the section it is for. It saves when you choose. It can't be sent for approval until it has one. See Divide a unit-price contract into sections.
The What it changes on the Schedule of Values card lists each of its PCOs' item lines, and the Markups and bond item its PCOs' overhead, profit and bond become.
When you record the owner's approval:
- Each new item is added to the schedule of values in the change order's section. An item without a number, or whose number has since been taken, is given the next free number.
- Each quantity change and unit price change is made on its item: its contract quantity or unit price, and its value, change.
- Its markups and bond are added as one item of their own, marked Lump sum, so the schedule of values still comes to the revised contract sum.
- Its section's Authorized amount rises by the change order's amount.
Once approved, the card is called What it changed on the Schedule of Values.
Change a unit-price commitment
On a unit-price commitment's change order, click Add line: Add lines has the same three forms. The Item list offers only this commitment's items. A new item needs its Item number, cost code and cost type; a change on an item uses that item's cost code and cost type.
The change order's lines stay its own on the commitment, as on any commitment, so each change order is billed on its own. Once one is approved, each item it changed shows Revised under its description on the commitment's Schedule of values: its quantity, unit and unit price as its approved change orders left them, and its amount.
Lines from a Change Event, under the same Add line, copies the change event's new items onto a unit-price commitment, at their cost. A change on an item of the owner's contract isn't one of the commitment's items, so it isn't copied.
History
With Financials — Approve, the History link at the top of a change event or change order opens its audit. Each line's history shows its kind, its item, its quantity and unit price, and each change to them. When a change is approved, the item's own history keeps its quantity or unit price before and after, and the section's history keeps its authorized amount before and after.