A Unit price Prime Contract can be divided into sections: one for each payer or owner funding line under the one contract, such as a city's base work and a utility's water and sewer lines. Each contract sets up its own. A Lump sum Prime Contract doesn't have sections.
For the items themselves, see Price lines by quantity on a unit-price contract.
Add a section
With Financials — Edit, open Prime Contract. Once the schedule of values has items, a Sections card shows under it.
- Click Add section.
- Type the section's Name. Two sections on a contract can't share one.
- Type the Owner reference if the owner has one for it, such as their purchase order line.
- Type the Authorized amount: what the owner has authorized on it. Left empty, it is $0.00.
- Click Add section.
New sections go after the others.
Put an item in a section
An item is in one section, or in none.
- In the schedule of values, click the pencil in the item's Actions column, choose its Section and click Save.
- To take it out of sections, choose No section.
When you add a line with Add line, you can choose its Section there too. The Section box shows once the contract has a section.
Read the schedule of values by section
Once the contract has a section, the items are grouped by it, in the sections' order, a grid for each:
- Each section's heading shows its name, its owner reference, its Authorized amount and its subtotal, for example Base Bid subtotal, and how it stands: Matches the authorized amount, or how much it is over or under.
- Once pay applications have been submitted, the heading also shows what the section is Billed to date, and how far past its authorized amount if it is. See Find and settle overruns on a unit-price contract.
- Items in no section come last, under Not in a section, with their own Subtotal.
The grid also gets a Section column. Sections never change the contract sum: the lines total the same however the items are grouped.
A contract with no sections shows its items in one grid.
The Sections card
The Sections card lists each section with its Owner reference, Authorized, Items total, how it stands Against authorized, how many Items it has and what it is Billed to date.
- Rename it, or change its owner reference or authorized amount: click the pencil in its Actions column, change the boxes and click Save.
- Reorder: in the same form, under Order, use the arrows. Its items move with it.
- Remove: a section can be removed only once it has no items. Move them to another section, or choose No section for each. Then open the section's form and click Remove section, and confirm.
The arrows under Order in an item's form move it up or down among its own section's items.
If the contract is switched to Lump sum
While the Prime Contract is a Draft, switching it to Lump sum hides its sections. Switched back to Unit price, its sections and each item's section are as they were.
History
With Financials — Approve, History at the top of the Prime Contract page opens the Financials Audit: each section added, renamed, reordered, given a new authorized amount or removed, and each item put in or taken out of a section, with the old and new value.