Financials is an add-on. If your company has it, each project's menu has a Financials group, and Budget in it is the project's cost budget, by cost code and cost type. It is separate from the schedule of values the owner is billed against.
The page has three tabs: Lines, Budget Changes and Contingency. This article is about Lines. For the other two, see Move money between budget lines and draw from contingency.
If your company has renamed "Budget", "Budget Change" or "Estimate" under Settings → Financials, the page uses your words.
Build the budget
The budget is built from the project's Original Estimate. Until the estimate has been locked, the page says No budget yet. with Import the estimate first. or Lock the estimate first., and Open the Estimate. See Check and lock the Original Estimate.
With Financials — Edit, once the estimate is locked, click Build the budget. The budget starts as a Draft, with one line for each cost code and cost type in the estimate. Estimate lines with the same cost code and cost type are added together into one line. Each line's Original starts at its Estimate; a credit in the estimate starts at nothing.
The budget's status (Draft, In review or Locked) shows under its title.
Read the grid
Each line shows its Cost code and Cost type. The other columns are:
- Estimate: what the Original Estimate had for it. It never changes.
- Δ vs estimate: the Original less the Estimate.
- Original: the budget for the line.
- Approved changes and Pending: what approved Budget Changes, and those waiting for approval, move onto the line. Money moved off it is a minus.
- Revised: the Original plus approved changes.
- Committed: what approved commitments' lines on the cost code and cost type come to, with their approved change orders and back charges. See Create a commitment and build its schedule of values and Change a commitment and charge costs back to a vendor.
- Job-to-date and To complete: the cost so far and the cost still to come, where someone has entered them. A box nobody has filled in stays empty.
- Projected (EAC): with Job-to-date and To complete both entered, the larger of Job-to-date plus To complete and Committed plus Pending. Without them, the larger of Revised and Committed, plus Pending.
- Over/(Under): Projected less Revised. Under shows in brackets; a line projected over is in red.
Quantity can be added from Columns: the line's quantity and unit, for example 4,245 LF, when every Original Estimate line on that code and type has a quantity in the same unit.
The tabs above the grid narrow it to All, Projected over or Contingency lines. Use Columns to choose and order the columns, click a heading to sort, search, filter and save the view. The Total row at the foot adds up the lines showing, and stays in view while the lines scroll. The cost code column stays put when you scroll sideways. Click the Full screen icon beside Columns to give the grid the whole window; Esc exits.
Under the grid, Protected profit is the Prime Contract's revised contract sum (its contract sum and the change orders the owner approved) less the revised budget. Until the Prime Contract has a contract sum, it says shown once the Prime Contract has a contract sum. It stays in StruXure.
If your company has Insights on, a line projected over its revised amount gets an Insight, listed under Insights on lines below the grid with the line's name, saying how much over and why: approved commitments, or Job-to-date and To complete. See Turn Insights on or off.
A line on a cost code your company marks as contingency is marked Contingency. See Choose which cost codes hold contingency.
Change a Draft
With Financials — Edit, while the budget is a Draft:
- Click the pencil in a line's Actions column. Type its new Original and click Save. Remove line takes it off the budget, after you confirm.
- Click Add line, choose a Cost code and a Cost type, type the Original and click Add line.
Send it for review and lock it
- With Financials — Edit, click Send for review and confirm. From then on only someone with Financials — Approve changes it.
- With Financials — Approve, check it, then click Lock the budget, or Send back to Draft for it to be changed again. If something stops it locking, the page lists it above the buttons.
Once locked, each line's Original is settled and can't be changed. The budget then changes only through Budget Changes.
Adjust the lines of a locked budget
With Financials — Edit, on a locked budget:
- Click Adjust lines. The grid shows each line's Cost type, Revised, a Change box, After (Revised with the change), Committed and Pending.
- In Change, type how much a line goes up, or down with a minus or in brackets.
- The bar under the grid says whether it Balances, or how much more is on than off (or off than on).
- Type the Reason.
- Click Send for approval (only once it balances), or Save draft. Cancel leaves without saving.
It is saved as one Budget Change, and you're taken to the Budget Changes tab. Money taken off a contingency line makes it a contingency draw; otherwise it is a transfer. To add a cost code and cost type the budget doesn't have yet, make a Budget Change on the Budget Changes tab instead. See Move money between budget lines and draw from contingency.
Enter job-to-date
With Financials — Edit, at any time, locked or not, click the pencil in a line's Actions column, type the Job-to-date and To complete, and click Save. Leave a box empty when it isn't known.
What goes to accounting
When the budget is locked, it goes to accounting if your company sends budgets when they are locked (Settings → Financials → Accounting). If accounting can't take it, it becomes a manual task. See Key a record in accounting by hand.
Accounting gets the job and each line's cost code, cost type and Original. Protected profit, the Estimate and Job-to-date stay in StruXure.
Once the budget is locked, the Accounting card, at the top, says where it stands: Not in accounting, On its way to accounting, Waiting for accounting to key it, In accounting with its ID, or Didn’t go through, and when it was last sent. Someone in the Accounting area can click Send to accounting at its foot to send a locked budget by hand, unless it is already waiting on accounting. Once accounting has it, this reads Send update; if its last send was cancelled, Send again.
History
With Financials — Approve you also see History at the top of the page. It opens the Financials Audit, filtered to the budget: when it was built, sent for review, sent back and locked, and each line added, changed or removed, with its old and new value and who did it.
Who can do what
- Financials — Read on the project: see the budget.
- Financials — Edit: build the budget, change a Draft, send it for review, adjust a locked budget's lines, and enter job-to-date.
- Financials — Approve: change it in review, send it back or lock it, and see its history.
- Accounting area: send a locked budget to accounting.