Financials is an add-on. If your company has it, each commitment's page has a Commitment Change Orders card once the commitment is approved.
A commitment's own lines can't change once it is sent for approval. After it is approved, what the vendor is owed changes only through its change orders. Each one has lines of its own, so it can be billed on its own invoice.
If your company has renamed "Commitment Change Order" or "Back Charge" under Settings → Financials, the pages use your words.
On a Unit price commitment, each line is a new item, or a quantity or unit price change on one of its items. See Change a unit-price contract.
See every one on the job
Click Changes in the project's Financials menu, then the Commitment Change Orders tab. It lists every commitment change order and back charge on the project with its Commitment, Number, Title, Vendor, Kind, Status and Amount, newest first, with a tab for each status. Use Columns to add Days or Started. Click a number or title to open one, or a commitment to open it. A new one is started from its commitment.
Two kinds
- Commitment Change Order: work added to the commitment or taken off it. Its lines can go either way.
- Back Charge: a cost charged back to the vendor, taken off what it is owed. Every line takes money off.
What the commitment's page shows
The Commitment Change Orders card shows the commitment's:
| Figure | What it is |
|---|---|
| Original | What its own lines come to. |
| Approved changes | What its approved change orders and back charges add, in brackets when they take off. |
| Revised | Original plus approved changes: what the vendor is owed. |
| Pending | What change orders waiting for approval would add. |
Below them is each change order with its Number, Kind, Title, Status, Days and Amount. Click the number to open one.
The commitment counts its Revised as committed: the budget's Committed column includes its approved change orders, on the cost code and cost type each line names.
Make one
With Financials — Edit, on a commitment that is approved, issued or executed:
- On the commitment's page, click New commitment change order or back charge at the top right of the Commitment Change Orders card.
- Choose its Kind, give it a Title, and, if you like, its Days (what it does to the vendor's schedule, either way) and a Reason. Click Create. It opens as a Draft, numbered the commitment's next.
- Click Add line above the Lines. Under Add lines, choose a Cost code and Cost type, type a Description, and the Amount. On a change order, choose under Money whether it Adds to the commitment or Takes off the commitment. On a back charge, type the Amount charged back. Click Add line, and Close when you're done.
The Lines card lists each line, money taken off in brackets, with a Total row. Above it, it says what the commitment is revised now, and what it will be once this is approved. To change a line's description or amount, click the pencil in its Actions column, change it and click Save. To take it off, click the pencil, then Remove line and Remove.
Under Details you can change the Title, Days, Change Events, Bills to owner and Reason while it is a Draft, then click Save. Bills to owner starts as the commitment's.
Take up change events
Under Details, pick the approved Change Events this change order takes up and click Save. Only approved change events on the project are offered. They show as links on the change order.
To copy a change event's lines onto it, click Add line, choose the event under Lines from a Change Event, and click Copy lines. Each line comes at its cost. From an owner change or allowance, only the lines a subcontractor does are copied, without your markup. On a back charge, each copied line takes money off.
See Record a change and price it.
Send it for approval
When its lines are right, click Send for approval. If nothing on its approval route applies at its amount, the button is Submit instead, and it is approved as soon as you click it. Until then the page says what is wrong:
- it needs at least one line;
- a change order whose lines come to nothing changes nothing;
- a back charge only takes money off;
- nothing can take the commitment below nothing.
It goes through the project's approval route for commitment change orders, at the money it moves either way, so a large back charge is approved like a large change. The card at the top of the page shows its whole life, left to right: Draft, Sent for approval, each step of its route, then Approved. Each stage it has reached says who took it there and when, the one it is in is marked as current, and a step still to decide says who it is waiting on. A returned one says on Draft who returned it and why; a void one ends at Void, with who voided it. Once there is nothing left to do on it, the card closes to one line, with Accounting beside it; click Show steps to open it. If no step applies to that amount, it is approved at once. See See and set who approves on a project.
While it waits, its lines can't be changed, and its money shows in the commitment's Pending. To change it again, open the ⋯ menu at the top right and click Take back to Draft.
Approve or return it
When it is your turn, the card at the top of the page says Your approval is needed. and has Return and Approve. Return asks Why is it returned? before it goes. Returned, it is a Draft again.
The last approval checks it again against the commitment as it is then. If it would take the commitment below nothing, it is refused.
Once approved, its money moves into the commitment's Approved changes and Revised. An approved change order can't be voided or changed. To move it back, make another one.
Void one
Void a Draft with Financials — Edit, or one waiting for approval with Financials — Approve: open the ⋯ menu at the top right, click Void, then Void again. It keeps its number and its history and changes nothing on the commitment.
Voiding a commitment voids its change orders that aren't approved yet. A commitment with an approved change order can't be voided.
What goes to accounting
When it is approved, a change order goes to accounting as its own record, if your company sends commitment change orders when they are approved (Settings → Financials → Accounting). Accounting gets the job, the commitment's number and its ID in accounting, the vendor and its vendor ID, the change order's number, kind, title, reason, days and bills to owner, its total, and each line's cost code, cost type, description and amount. On a unit-price commitment, if your accounting system takes quantities, each line also says whether it is a new item, a quantity change or a unit price change, with its item, quantity, unit and unit price. Money taken off is a minus, so a back charge goes as a negative change order. If accounting can't take it, it becomes a manual task. See Key a record in accounting by hand.
The Accounting card, at the top, says where it stands: Not in accounting, On its way to accounting, Waiting for accounting to key it, In accounting with its ID, or Didn’t go through with the reason. Someone in the Accounting area can click Send to accounting, then Send, to send an approved one that hasn't gone yet. It reads Send again if its last send was cancelled.
History
With Financials — Approve, click History at the top of the change order. It opens the Financials audit for it: when it was created, sent, approved, returned or voided, each field changed, the change events it took up, and each line added, changed or removed, with old and new values and who did it. The commitment's own history shows its approved changes before and after each approval.
Who can do what
- Financials — Read on the project: see a commitment's change orders.
- Financials — Edit: make a change order or back charge, change a Draft, send it for approval, take it back, and void a Draft.
- Financials — Approve: approve or return one when it is your turn, void one waiting, and see the history.
- Accounting area: send an approved change order to accounting.
Generate it as a document
The Change order document card makes the change order as a PDF from your company's Commitment change order template, or StruXure's built-in. See Generate a commitment's subcontract agreement.