Move money between budget lines and draw from contingency

Once the budget is locked, move money between its lines, or draw it from contingency, with a Budget Change sent for approval; see what is left of contingency; send an approved change to accounting.

Who this is forProject managers, Project executives, Accounting

Permission neededFinancials — Read to see them, Edit to make and send one, Approve to approve, void one waiting and see the history; Accounting — Edit to send one to accounting

Financials is an add-on. If your company has it, each project's menu has a Financials group. Open Budget in it: the Budget Changes tab lists the project's Budget Changes, and the Contingency tab shows what is left of contingency.

Once the budget is locked, each line's Original never changes. Money moves between lines only through a Budget Change. Until the budget is locked, both tabs say Not locked yet. Change its lines on the Lines tab. See Build, review and lock the budget.

If your company has renamed "Budget Change" or "Budget" under Settings → Financials, the pages use your words.

Two kinds

  • Transfer: money moved from one budget line to others, or back onto contingency.
  • Contingency draw: money taken off contingency onto the lines that need it.

A contingency line is a budget line on a cost code your company marks as contingency. Money comes off a contingency line only by a contingency draw. See Choose which cost codes hold contingency.

Make one from the budget's lines

The quickest way is on the budget's Lines tab: click Adjust lines, type each line's change, give a reason and click Send for approval or Save draft. See Build, review and lock the budget.

Make one on the Budget Changes tab

With Financials — Edit:

  1. On the Budget Changes tab, click New budget change.
  2. Choose its Kind, give it a Title and, if you like, a Reason, and click Create. It opens as a Draft, numbered the project's next.
  3. Click Add line. Choose a Budget line, choose whether the money Comes off this line or Goes onto this line, type the Amount and click Add line. Each budget line appears once on a change.
  4. To move money onto a cost code and cost type the budget doesn't have yet, choose New line and pick its cost code and cost type in New line: cost code and New line: cost type. The budget gains that line once the change is approved, with an Original of nothing. Money can't come off a line the budget doesn't have.

The Lines grid shows each line's Cost code, Cost type, Revised now, This change (money off a line is in brackets) and Revised once approved. Under it, the page says what the lines come to, for example Comes to $0.00: it balances. While it is a Draft, click the pencil in a line's Actions column to change its Money or Amount and click Save, or click Remove line and confirm to take it off.

Under Details you can change the Title and Reason while it is a Draft, and click Save.

The page's header shows its status, kind, title and the money it moves. Back to the budget returns to the Budget Changes tab.

Send it for approval

When its lines are right, click Send for approval. If nothing on its approval route applies at its amount, the button is Submit instead, and it is approved as soon as you click it. Until then the page says what is wrong, after Before it is sent for approval:

  • money off and money on must match, so the budget's total stays the same;
  • no line can go below nothing;
  • a transfer can't take money off contingency, and a contingency draw takes money off contingency only, onto lines that aren't contingency.

It goes through the project's approval route for Budget Changes, at the money it moves. The card at the top of the page shows its whole life, left to right: Draft, Sent for approval, each step of its route, then Approved. Each stage it has reached says who took it there and when, the one it is in is marked as current, and a step still to decide says who it is waiting on. A returned one says on Draft who returned it and why; a void one ends at Void, with who voided it. Once there is nothing left to do on it, the card closes to one line, with Accounting beside it; click Show steps to open it. If no step applies to that amount, it is approved at once. See Set who approves financial documents on a project.

While it waits, its lines can't be changed, and each line's money shows in the budget's Pending column. To change it again, open the ⋯ menu at the top right and click Take back to Draft.

Approve or return it

When it is your turn, the card at the top of the page says Your approval is needed. and has Return and Approve. Return asks Why is it returned? before it goes. Returned, it is a Draft again.

The last approval checks it again against the budget as it is then. If another change has used the money since, it is refused and says which line.

Once approved, each line's money moves into the budget's Approved changes, and so its Revised. The budget's Insights read the new revised amounts.

An approved Budget Change can't be voided or changed. To move the money back, make another one.

Void one

Void a Draft with Financials — Edit, or one waiting for approval with Financials — Approve: open the ⋯ menu at the top right and click Void. You're asked first. It keeps its number and its history and moves nothing.

The Budget Changes tab

The grid lists each Budget Change's Number, Title, Kind, Status, the date it was Made, and what it Moves. The tabs above it narrow it by status. Click a number or title to open it.

Contingency

The Contingency tab lists each contingency line with its Cost code, Cost type, Original, what approved draws Drawn, what transfers Added back, what is Left, and the Draws waiting for approval. The budget's Lines tab marks each contingency line Contingency.

What goes to accounting

When it is approved, a Budget Change goes to accounting as its own record, if your company sends Budget Changes when they are approved (Settings → Financials → Accounting). Accounting gets the job, its number and kind, its title and reason, the money it moves, and each line's cost code, cost type and amount, money off a line as a minus. If accounting can't take it, it becomes a manual task. See Key a record in accounting by hand.

The Accounting card, at the top, says where it stands (for example Not in accounting or In accounting with its ID) and when it was last sent. Someone in the Accounting area can click Send to accounting to send an approved change that hasn't gone yet. It reads Send again if its last send was cancelled.

History

With Financials — Approve you also see History at the top of the page. It opens the Financials Audit, filtered to this Budget Change: when it was created, sent, approved, returned or voided, and each line added, changed or removed, with its old and new amount and who did it.

Who can do what

  • Financials — Read on the project: see Budget Changes and the contingency ledger.
  • Financials — Edit: make a Budget Change, change a Draft, send it for approval, take it back, and void a Draft.
  • Financials — Approve: approve or return one when it is your turn, void one waiting, and see the history.
  • Accounting area: send an approved Budget Change to accounting.