Force account prices extra work the way a change order proposal does: the crew's hours at straight and overtime rates, the equipment's hours at its hourly rate, material and subcontract costs, each with its compensation, then the bond. For change events in general, see Record a change and price it.
Set the rates
Settings → Financials → Force account (Settings — Edit):
- Markups: Labor compensation, Labor burden, Equipment, Material, Subcontract and Bond, each a percentage.
- Labor: each class with its ST rate and OT rate.
- Equipment: each piece with its Unit and Rate, and its Source.
EquipmentWatch rates explains where equipment rates come from with a subscription, and Load sample rates adds a sample fleet and crew to price with.
Price the work
- Open a Draft change event. In Force account, click New force account.
- Enter the Work, its Quantity and Unit (the detail prices one unit), the Cost code, and Why it's extra.
- Under Labor, Equipment, Material and Subcontract, click Add for each row. Choosing a class or piece of equipment fills its rate.
- Proposal, on the right, shows each part with its compensation, the subtotal, the bond, the price Per unit and the total.
- Click Save and add to the change event. On a unit-price contract the line is a new item, the quantity at the price per unit; otherwise it is a cost line with no further markup.
Pull crew hours from HeavyJob explains where the hours come from with the HeavyJob connection, and Add sample hours fills in a sample crew and equipment from your rates.
Change it
Open the worksheet from the change event's Force account card, change it, and click Save and update the line. A worksheet is priced with the markups as they were when it was last saved.