Financials is an add-on. If your company has it, each project's menu has a Financials group, and Commitments in it lists the project's subcontracts, purchase orders and work orders: each one's number, kind, title, vendor, status and amount. Use Columns to choose what shows, click a heading to sort, and search or filter the list.
If your company has renamed "Commitment", "Buyout Log" or "Budget" under Settings → Financials, or renamed the kinds, the pages use your words.
Create a commitment
With Financials — Edit:
- Click New at the top of the Commitments page.
- Type a Title, such as the trade.
- Choose the Vendor. The project's active companies are listed. To give a commitment to another company, add it to the project's Directory first. If no company is on the project yet, the page says No company is on this project yet. Add one in the project’s Directory first.
- It is a Subcontract unless you choose otherwise: to make a Purchase Order or Work Order, open Kind in the Details panel on the right.
- Click Create.
It is made as a Draft and opens on its own page. Its number is given now, from your company's pattern for its kind, and never changes. See Set what commitments are called and how they are numbered.
Build its schedule of values
The Schedule of values card lists what the vendor will bill against. Each line has a cost code, a cost type (shown by its name), a description and an amount, and Source says whether it came from the Buyout Log or was Added here. On a unit-price commitment the lines are items, with their Item, Owner item, Owner reference, Quantity, Unit and Unit price. A cost code can appear on more than one line.
On a Draft, click Add line above the lines. Under Add lines:
- From the Buyout Log lists the scopes this commitment can take: those the Buyout Log gives to this vendor, and those not given to anyone yet. Tick the scopes and click Add as lines. Each becomes a line at its revised amount. A scope not given to anyone is given to this vendor. A scope already on another commitment isn't listed. See Build and keep the Buyout Log.
- Or add a line adds one by hand: choose the Cost code and Cost type, type the Description and Amount, and click Add line. On a unit-price commitment the first row is Cost code, Cost type, Item, Description, Quantity, Unit, Unit price and Lump sum, and the second Owner item and Owner reference. A red asterisk marks each box it needs. An amount in brackets or with a minus is a credit. When the Buyout Log has no scopes to offer, this is the only form.
Once the line is added, the panel closes and the line is in the list. The lines show a Total row.
To change a line, click the pencil in its Actions column, change it and click Save. To take it off, click the trash can beside the pencil, then Delete.
Who it is between
Beside Details, the Contract card reads as the commitment does on paper: From your company and To the vendor, with the addresses and phone numbers Company Setup and the Directory have for them.
Attach the signed contract
The Attachments card holds the commitment's files: the signed contract, and anything that goes with it. With Financials — Edit, drop a file on it or choose one, in any state; click the trash can beside a file to remove it. Anyone who can see the commitment can open them.
Fill in its details
On a Draft, with Financials — Edit, click a value in the Details card to change it: Title, Vendor (another company on the project), Retainage, Bills to owner, Start, Estimated completion and Scope. It saves when you finish. The Kind can't be changed.
Scope takes formatting: bold, italic, underline, bulleted and numbered lists, from the bar over it. The commitment's PDF prints it formatted, and accounting gets its words.
Choose its contract type
A commitment is Lump sum or Unit price. A new one starts as your company's choice for new commitments, set under Settings → Financials → Contract types and units. See Set contract types and units.
On a Draft, click Contract type in the Details card and choose the other type. Once it is sent for approval, the type is fixed, and Details shows it as text.
Made Unit price, each line becomes 1 LS at its amount; made Lump sum, each keeps its amount and drops its quantity. On a unit-price commitment, each line is a quantity at a unit price. See Price lines by quantity on a unit-price contract.
Once a change order on a unit-price commitment is approved, each item it changed shows Revised under its description: its quantity and unit price as its change orders left them, and its amount. See Change a unit-price contract.
See where it stands
The card at the top of a commitment's page shows its whole life, left to right: Draft, Sent for approval, each step of its approval route, then Approved, Issued, Executed and Closed. Each stage it has reached says who took it there and when: who made it, who sent it, who approved each step, who issued it and who marked it executed. The stage it is in is marked as the current one, and the stages still to come are shown after it. On a Draft, the steps are the ones its route has at its amount now. Once there is nothing left to do on it, the card closes to one line, with Accounting beside it; click Show steps to open it.
A returned commitment says on Draft who returned it, at which step, and why. A void one ends at Void, with who voided it and when.
The next thing to do is on the same card, for whoever may do it: Send for approval, Approve and Return, Issue, Mark executed, or Step back.
Send it for approval
When its vendor is still on the project and it has at least one line, click Send for approval. Until then, the page says what it still needs. If nothing on its approval route applies at its amount, the button is Submit instead, and it is approved as soon as you click it.
It follows the project's approval route for commitments, at its amount. See Set who approves financial documents on a project. If no step of the route applies to that amount, it is approved straight away.
While it waits, its lines and details don't change. The card at the top of the page shows who approved each step and when, and who the current step is waiting on. To change it, open the ⋯ menu at the top right and click Take back to Draft.
Approve or return it
When it is your turn, the card at the top of the page says Your approval is needed. and has Return and Approve. Return asks Why is it returned? before it goes. Approving moves it on to the next step, or makes it Approved after the last. Returning makes it a Draft again.
Once approved, its amount counts as Committed on the budget and on the Buyout Log. If your company sends commitments to accounting when they are approved, it goes to accounting now. See Send it to accounting.
Change it once approved
Once a commitment is approved, its own lines don't change. Change what the vendor is owed with a commitment change order, or charge a cost back with a back charge, from the Commitment Change Orders card on its page. The card shows its Original, Approved changes, Revised and Pending. Its Revised is what counts as Committed on the budget. See Change a commitment and charge costs back to a vendor.
Issue it
An approved commitment is issued to its vendor only once the project's Prime Contract is executed. You can create, build and approve it before then. See Keep the Prime Contract and execute it.
With Financials — Edit, when the Prime Contract is executed, the card at the top of the page says Approved. Ready to issue. and has Issued on and Issue. Issued on starts at today; change it if it was issued on another day, then click Issue. It becomes Issued.
Until it can be issued, the page says why after Before it is issued:, for example that it is held until the Prime Contract is executed. If the Prime Contract is closed, reopen it first. Its vendor must still be on the project.
Once issued, a commitment can't be voided.
Keep its dates
Once it is issued, the Details card has Issued, Sent and Returned: when it was issued, sent to the vendor, and returned signed. Once it is executed, it has Executed too. With Financials — Edit, click a date to change it. Each date must be on or after the one before it.
The Buyout Log shows these dates for each scope on the commitment.
Mark it executed
When the vendor's signed copy is back, on the card at the top of the page, type the date in Executed on (it starts at today) and click Mark executed. It becomes Executed, and each scope it covers shows as Executed on the Buyout Log.
Step it back a stage
If it was issued or marked executed too early, someone with Financials — Approve can step it back one stage: from Executed to Issued, or from Issued to Approved.
- On the card at the top of the page, click Step back to Issued (or Step back to Approved). If the card is closed to one line, click Show steps first.
- Under Why is it stepped back?, say why.
- Click Step back.
Stepped back to Issued, its executed date is cleared and its scopes on the Buyout Log are no longer executed; mark it executed again when the signed copy is back. Stepped back to Approved, its issued, sent and returned dates are cleared, and it is issued again with Issue. The stage it went back to says who stepped it back, when and why, and the change is in its history.
Nothing steps back past Approved: its amount still counts as committed, and it changes through a change order, or is voided. If your company sends commitments to accounting when they are issued or executed and accounting already has it from that stage, it isn't stepped back. If it was still waiting to go, that send is cancelled, and it goes again when it reaches the stage again.
Download it as a PDF
Click PDF at the top right of its page. The PDF has its number, status, vendor, your company, its terms and dates, its scope, its schedule of values with the total, and a line for each side to sign. It shows the commitment as it is when you download it.
For the agreement itself, worded by your company's document template, use the Subcontract agreement card (see Generate a commitment's subcontract agreement).
Anyone with Financials — Read on the project can download it.
Send it to accounting
Your company chooses when commitments go to accounting: when they are approved, when they are issued, or when they are executed. See Connect Financials to your accounting system. Accounting gets its job, number, kind, vendor and the vendor's ID in accounting, its terms and dates, and its schedule of values. On a unit-price commitment, if your accounting system takes quantities, each item goes with its quantity, unit and unit price; if it doesn't, the amounts go alone. If your accounting system can't take it, it becomes a Manual Task. See Key a record in accounting by hand. If its vendor has no vendor ID in accounting yet, it waits on the Accounting Queue until someone enters it; see Link a company to accounting.
Once a commitment is approved, the Accounting card, at the top beside where it stands with approval, says where it stands: Not in accounting, On its way to accounting, Waiting for accounting to key it, In accounting with its ID, or Didn’t go through with the reason. With Accounting — Edit, click Send to accounting, then Send, if it hasn't been sent. If it has changed since it was last sent, this reads Send update; if its last send was cancelled, Send again. It can't be sent again while an earlier send is still waiting. With Accounting — Read, Open the accounting queue on the card opens the Accounting Queue.
See it on the Buyout Log
Each scope on a commitment shows the commitment's number in the Buyout Log's Commitment column. Click the number to open it. A scope on a commitment can't be removed from the Buyout Log.
See what is billed on it
Once it is approved, its page has a Sub Invoices card when it has a sub invoice, or when you may start one: its Revised, what is Billed on it, what is Left to bill and the Retainage held, then each sub invoice. With Financials — Edit, click New sub invoice in the card's header to start one for this commitment. See Enter a sub invoice.
Void it
Void takes a commitment out of use: open the ⋯ menu at the top right, click Void, then Void again. It keeps its number and its history, and the scopes it covered are open again on the Buyout Log. A Draft can be voided with Financials — Edit; one waiting for approval or approved needs Financials — Approve. An issued commitment can't be voided, nor one with an approved change order or a sub invoice sent for review. Voiding a commitment voids its change orders that aren't approved yet, and its Draft sub invoices.
If it was waiting to go to accounting, that is cancelled. If accounting already has it, it is removed from accounting, or a Manual Task asks accounting to remove it.
Delete one made in error
A Draft or Void commitment that has no sub invoices and was never sent to accounting can be deleted. With Financials — Edit, open the ⋯ menu at the top right, click Delete, then Delete again. It moves to the Recycle Bin, and the scopes it covered are open again on the Buyout Log. Anything further along is voided instead.
Recycle Bin, under the list of commitments, shows the deleted ones with who deleted them and when:
- Restore brings one back as it was, with Financials — Edit. If a scope it covered is on another commitment now, it can't be restored until that scope is free.
- Delete forever removes it for good, with its lines, change orders and files, and Empty the Recycle Bin removes them all. Both need Financials — Approve. Its number stays used: the next commitment is numbered after it.
See its history
With Financials — Approve, click History at the top of the commitment. It opens the Financials audit for the commitment and its lines: who made each change and when, and the value before and after. A step back shows there with its reason.