Financials is an add-on. If your company has it, each project's menu has a Financials group, and Buyout Log in it shows each scope of the job, who it is bought out to, and for how much.
If your company has renamed "Buyout Log", "Estimate" or "Commitment" under Settings → Financials, the page uses your words.
Build the Buyout Log
The Buyout Log is built from the project's Original Estimate. Until the estimate has been locked, the page says Import the estimate first. or Lock the estimate first., with Open the Estimate. See Check and lock the Original Estimate.
With Financials — Edit, once the estimate is locked, click Build the Buyout Log. It starts with one row for each line in the estimate's work section, in the estimate's order. General conditions lines aren't bought out, so they aren't on it.
Each row's sub starts as the bid the estimate line was priced from: the bid marked as used, or, if none was, the only qualified bid. If exactly one company in the Directory has that name, the row is linked to it. Otherwise the row shows the name as the estimate had it, marked (not in the Directory), until you pick the company. A line with no such bid starts Not assigned.
Read the columns
| Column | What it shows |
|---|---|
| Cost code and Cost type | The row's cost code and cost type. |
| Trade | The trade or scope. |
| Sub | The company the scope is meant to go to. |
| Commitment | The number of the commitment that buys it out. Click it to open the commitment. |
| Original estimate | What the Original Estimate had for it. It never changes. A row added later has none. |
| Adjustment | Money moved onto the scope, or off it (in brackets). |
| Revised | The original estimate plus the adjustment. |
| Committed | What that commitment's lines for the scope come to, once it is approved. |
| Delta | Revised less Committed: what is left to buy out. Bought over shows in red, in brackets. |
| Projected start | When the scope is expected to start. |
| Issued, Sent, Returned, Executed | The commitment's dates. |
| License | The sub's license from its vendor profile: None on file, Current or Expired (in red), with the soonest expiry date. |
| Notes | Anything else about the scope. |
Bought out (Open, Committed or Executed) can be added from Columns. The tabs above the grid narrow the rows the same way.
Use Columns to choose and order the columns, click a heading to sort, search, filter and save the view. The Total row at the foot adds up the money columns of the rows showing. Click the Full screen icon beside Columns to give the grid the whole window; Esc exits.
Change a row
With Financials — Edit, click the pencil in the row's Actions column. Its form opens beneath it. Change any of:
- Trade or scope, Cost code and Cost type
- Sub: pick a company from the Directory. Any company can be picked, whether or not it is on the project's team yet. Clear it to take the company off. A name the estimate gave the row stays until a company is picked.
- Adjustment: type an amount, or one in brackets or with a minus to move money off the scope
- Projected start and Notes
Click Save. The original estimate stays as the estimate had it; move money with the adjustment.
Remove row takes a row off the log, after you confirm. Its history is kept. A row on a commitment can't be removed; take it off the commitment first.
When a scope not given to anyone is added to a commitment, its Sub becomes the commitment's vendor. See Create a commitment and build its schedule of values.
Add a row
Click Add row, fill in the same fields and click Add row. A row added here has no original estimate: its money is its adjustment. A contingency row is an adjustment alone.
History
With Financials — Approve you also see History at the top of the page. It opens the Financials Audit, filtered to the Buyout Log: each row added, changed or removed, with its old and new value and who did it.
Who can do what
- Financials — Read on the project: see the Buyout Log.
- Financials — Edit: build it, change, add and remove rows, and pick each row's sub.
- Financials — Approve: see its history.