Choose which cost codes hold contingency

Mark the cost codes that hold contingency, so money comes off a budget line on one of them only by a contingency draw.

Who this is forCompany admins

Permission neededSettings — Read to see, Admin to change

Financials is an add-on. If your company has it, Financials appears on the Settings page under Projects, and its Contingency card opens this page.

Contingency cost codes lists your company's cost codes. Tick each one that holds contingency and click Save. Without Settings — Admin, you see the ones ticked.

A budget line on a contingency cost code is a contingency line, on every project:

  • money comes off it only by a contingency draw, a kind of Budget Change;
  • the project's Budget Changes page shows what is left of it;
  • the budget marks it Contingency.

Unticking a cost code makes its lines ordinary lines from then on. What was drawn from them stays drawn.

If there are no cost codes yet, the page links to Cost codes and cost types to add them. See Set up cost codes and cost types and Move money between budget lines and draw from contingency.