Set the markups a change is priced with

Set the overhead and profit added to work by your own forces and by subcontractors, and the bond, that owner changes and allowances are priced with.

Who this is forCompany admins

Permission neededSettings — Read to see, Admin to change

Financials is an add-on. If your company has it, Financials appears on the Settings page under Projects, and its Change markups card opens this page. The card shows the markups you have now.

Owner changes and allowances are priced as potential change orders. Set what they add to the cost of the work:

  • Work by our own forces: Overhead on our own work % and Profit on our own work %.
  • Work by subcontractors: Overhead on subcontracted work % and Profit on subcontracted work %.
  • Bond: Bond %.

Each is a percentage from 0 to 100. Leave a box empty for none. Click Save.

Until you set them, there are no markups: a change is priced at its cost.

How a change is priced

  • A line's markup is its cost times its overhead and profit together.
  • The bond is the cost and markup together, times the bond.
  • The potential change order's amount is the cost, the markup and the bond.

For example, with 5% overhead and 5% profit on your own work, 5% overhead and no profit on subcontracted work, and a 1.2% bond: $10,000 of your own work and $20,000 of a subcontractor's come to $30,000 cost, $2,000 markup and $384 bond, $32,384 in all.

A new line on a change event starts from the overhead and profit for who does the work, and a new change event starts from the bond. Either can be changed on the change event. Changing them here doesn't change lines or change events already made.

Contingency draws, internal changes, work orders and back charges are cost only: they have no markup and no bond. See Record a change and price it.