If you're named as the RFI manager on an RFI, you're the person who gets it answered. Once the responses are in, the RFI is waiting on you. This is the whole path.
1. Find the RFIs waiting on you
- Open the project and choose RFIs in the sidebar.
- Click Waiting on me in the filter row. The list shows only the RFIs waiting on you.
To keep it with other filters, save it as a view. See Save a view of the RFI list.
2. Check who still owes a response
Open the RFI. Under Assignees (To) in the column on the right, each person ticked Required says responded or not yet responded. If someone else needs to act first, such as a consultant the architect has asked, pass it to them with Pass at the top of the page. See Who an RFI is waiting on.
3. Mark the answer official
Read the responses in the Responses card and click Mark as Official on the one the work is to be carried out to. The timeline at the top moves on to Closed.
See Mark the official response and close an RFI.
4. Close and distribute it
Click Close and distribute at the top of the page. Check the To and CC lines, choose the PDF, and click Close and distribute. The RFI is closed, no longer waiting on anyone, and everyone chosen is emailed its PDF with the answer. To close it without emailing anyone, click Close only instead. See Mark the official response and close an RFI.
If the question changes
Only RFI admins can reword the question. They can correct it in place while the RFI is open, or create a new revision if the question itself changes. A revision makes the RFI Open again, even if it was closed, and it goes back to waiting on the required assignees. See Change the question with a new revision.
What your access allows
- With Read access to RFIs, you can pass an RFI you manage and make it private or public, but not mark a response official, distribute or close it.
- With Respond, you can do every step above on the RFIs you manage.
- RFI admins can do all of it on every RFI.